Source of Funds
Existing Budget:
Water Fund $200,000
Proposed Budget Transfers:
Water Fund from Project 53250 $3,092,000
TOTAL $3,292,000
Estimated Expenditures
Construction Contract $2,831,970
Project Design $62,000
Estimated Surveying, Inspection, Testing, 4.0% $114,000 and Contract Administration
Contingencies 10.0% $284,000
TOTAL $3,291,970
Bid Opening: June 7
th, 2023
Engineer's Estimate: $3,100,000
Contractor Location Bid Total
1. Big Ben, Inc. Irvine, CA $2,831,970.00
2. Bonadiman Water, Inc. Riverside, CA $3,008,660.00
3. Teichert Energy & Utilities Group Long Beach, CA $3,431,700.00
4. Palp, Inc. Dba Excel Paving Long Beach, CA *$3,679,330.00 *= Submitted bid amount was $3,674,130.00, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $3,679,330.00 ATTACHMENT 1 - BUDGET DATA SHEET
WATER MAIN REPLACEMENT - VARIOUS LOCATIONS
Summary of Bids
PROJECT NO. 53026