BID PROPOSAL

BALCOM ALLEY SEWER REPLACEMENT
PROJECT NO. 51032

ESTIMATED

NO ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 MOBILIZATION 1 LS 15,000 15,000
2 WATER POLUTION CONTROL 1 LS 8,000 8,000
3 TRAFFIC CONTROL 1 LS 29,000 29,000
4 REMOVE EXISTING & INSTALL 8" VCP 562 LF 225 126,450
5 REMOVE EXISTING MANHOLE 2 EA 2,000 4,000
6 ABANDON MANHOLE 1 EA
2,000 2,000
ABANDON 10" VCP 246 LF 10 2,460
8 INSTALL PRECAST SEWER MANHOLE 3 EA 12,000 36,000
RE-INSTATE LATERAL 12 EA 2,500 30,000
10 6" PIPE BURST 174 LF 174 30,276
11 INSTALL 6" HDPE 11 LF 174 1,914
12 REMOVE EXISTING & INSTALL SEWER
CLEANUT 1 EA 4,000 4,000
13 CONSTRUCT ALLEY RETURN 620 SF 30 18,600
14 CONSTRUCT ALLEY GUTTER 20 LF 100 2,000
15 2" COLDMILL 1500 SF 2 3,000
16 3" COLDMILL 8800 SF 1.50 13,200
17 AC DIGOUTS* 500 SF 3 1,500
18 AC PAVEMENT 190 TON 260 49,400
19 ADJUST WATER VALVE TO GRADE 2 EA 800 1,600
20 ADJUST MH TO GRADE 3 EA 1,000 3,000
Base Bid Total $ 381,400

TO BE SUBMITTED WITH BID
BD-14

BID PROPOSAL

BALCOM ALLEY SEWER REPLACEMENT
PROJECT NO. 51032

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
"Bid iter is as needed and not subject to Greenbook sections 7-3.5.2 or 7-3.5.3 Unit prices are required for all bid items.

The Bidder shall total his/her bld. Unit prices shall prevall In case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Attemates after award.

Changes to either Unit Price or Amount shall be striked-out and initialed.

Hema of work not specifically listed shall be included In the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additonal compensation will be paid therefor.

If the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company_ BONADIMAN WATER, INC.

Name LEON LOPEZ, PRESIDENT
Signature
Address_ 19641 SEATON AVE
City & Zip Code PERRIS, CA 92570
Phone Number (951) 657-0200
License Number 1045913-A