ATTACHMENT 2

BID PROPOSAL

BROOKDALE PLACE STREET IMPROVEMENTS
PROJECT NO. 44064

ESTIMATED
NO. ITEM QUANTITY| UNIT| UNIT PRICE AMOUNT
1 Mobilization (3% max) 1 LS $9,500.00 9,500.00
2 Water Pollution Control 1 LS $ 5,000.00 $ 5,000.00
3 Traffic Control 1 LS $ 20,000.00 $ 20,000.00
4 Roadway Excavation 360 CY $ 190.00 $ 68,400.00
5 2" Coldmill 1425 SF $ 3.00 $ 4,275.00
6 Aggregate Base 353 TON $ 70.00 $ 24,710.00
AC Pavement 363 TON 184.00 $ 66,792.00
8 AC Pavement for Alleys 6 TON $ 805.00 $ 4,830.00
9 Curb & Gutter 630 LF $ 85.00 $ 53,550.00
10 Construct Alley Return w/ Access Ramps 830 SF $ 30.00 $ 24,900.00 11 Construct Alley Gutter 32 SF $ 100.00 $ 3,200.00
12 Sidewalk 142 SF $ 16.00 $ 2,272.00
13 Driveway Approach 230 SF $ 25.00 $ 5,750.00
14 Adjust Water Valve to Grade 5 EA 2,500.00 $ 12,500.00 15 Adjust MH to Grade 2 EA $ 2,500.00 $ 5,000.00
16 Traffic Striping and Signage 1 LS $ 6,000.00 $ 6,000.00 17 Street Light Conduit Repair 100 LF $ 25.00$ 2,500.00 18 Street Light Conduit w/ conductors and pull box 40 LF $ 200.00 $ 8,000.00 Base Bid Total $ 327,179.00
Additive bid Alternates
A1 Construct Alley Return w/ Access Ramps 1150 SF $ 30.00 $ 34,500.00 A2 Construct Alley Gutter 64 SF $ 100.00 $ 6,400.00
A3 AC Pavement 6 TON $ 805.00 $ 4,830.00
A4 Adjust Water Valve to Grade within Alley Return 2 EA $ 2,500.00 $ 5,000.00 Grand Total (Base+Additive Alternates) $ 377,909.00

TO BE SUBMITTED WITH BID
BD-18

BID PROPOSAL

BROOKDALE PLACE STREET IMPROVEMENTS
PROJECT NO. 44064

ESTIMATED
NO. ITEM QUANTITY UNIT | UNIT PRICE AMOUNT
Unit prices are required for all bid items.

The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award.

Changes to either Unit Price or Amount shall be striked-out and initialed Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.
if the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company Towo Enterprise Inc
Name Yun Su Chung
Signature vubm
Address 2536 Fender Ave Suite D
City & Zip Code Fullerton, CA 92831
Phone Number 714-770-0379
License Number 986567

TO BE SUBMITTED WITH BID