ATTACHMENT 1 – BUDGET DATA SHEET

KIMBERLY AVENUE SEWER REPLACEMENT PROJECT
Project No.: 51031
Source of Funds
Existing Budget:

Sewer Enterprise Fund $25,000
Proposed Budget Transfers:

Sewer Enterprise Fund from Project 51419 $294,000
TOTAL $319,000
Estimated Expenditures
Staff Design, Administration and Processing $18,927
Construction Contract $249,250
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $24,925
Contingencies (10%) $24,925
TOTAL $318,027
Summary of Bids
Bid Opening: October 6, 2023
Engineer’s Estimate: $175,000
Contractor
Location
Bid Total

1. Big Ben, Inc.

Irvine
$249,250

2. Dominguez General Engineering, Inc.

Pomona
$269,000

3. Williams Pipeline Contractors
Mission Hills
$353,150