ATTACHMENT 1 – BUDGET DATA SHEET
CURB & GUTTER AND SIDEWALK PROJECT FY 22-23
Project No.: 44794
Source of Funds
Existing Budget:
Drainage Capital Outlay $450,000
Proposed Budget Transfers:
Drainage Capital Outlay from Project 44795 $202,000
TOTAL $652,000
Estimated Expenditures
Staff Design, Administration and Processing $36,500
Tree Investigation and Removals $58,000
Construction Contract $474,100
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $35,558
Contingencies (10%) $47,410
TOTAL $651,568
Summary of Bids
Bid Opening: October 10, 2023
Engineer’s Estimate: $563,500
Contractor
Location
Bid Total
1. CJ Concrete Construction Inc.
Santa Fe Springs
$474,100
2. Onyx Paving Company, Inc.
Anaheim
$505,000
3. Towo Enterprise Inc
Fullerton
$662,500
4. Bonadiman Water, Inc.
Perris
$614,100
5. Addison- Miller Inc.
Orange
$685,500
6. We R Builders
Glendale
$858,160