ATTACHMENT 1 – BUDGET DATA SHEET
BASQUE AVENUE STREET AND STORM DRAIN REHABILITATION PROJECT Project No.: 44071
Source of Funds
Existing Budget:
ARPA Fund $50,000
Proposed Budget Transfers:
ARPA Fund from Project 44589 $754,000
TOTAL $804,000
Estimated Expenditures
Staff Design, Administration and Processing $5,116
Construction Contract $638,920
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $63,892
Contingencies (15%) $95,838
TOTAL $803,766
Summary of Bids
Bid Opening: January 18, 2024
Engineer’s Estimate: $582,000
Contractor
Location
Base Bid Total*
Bid Alternate
1. Towo Enterprise Inc.
Fullerton
$536,320.00
$102,600.00
2. Bonadiman Water, Inc
Perris
$563,900.00
$85,500.00
3. US Builders & Consultants Inc.
Irvine
$567,400.00
$69,511.50
4. Hardy & Harper, Inc.
Lake Forest
$576,999.00
$55,575.00
5. R.J. Noble Company
Orange
$588,822.50
$64,125.00
6. PALP, Inc. DBA Excel Paving Company
Long Beach
$614,998.00
$64,980.00
7. All American Asphalt
Corona
$649,649.00
$64,125.00
*Project awarded on base bid cost.