ATTACHMENT 1 – BUDGET DATA SHEET

CROWN AREA WATER MAIN REPLACEMENT PROJECT
Project No.: 53030
Source of Funds
Existing Budget:

Water Fund $75,800
Proposed Budget Transfers:

Water Fund from Project 53250 $1,024,200
TOTAL $1,100,000
Estimated Expenditures
Construction Contract $770,560
Project Design and Coordination $80,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $77,056
Contingencies (15%) $115,584
TOTAL $1,043,200
Summary of Bids
Bid Opening: January 17, 2024
Engineer’s Estimate: $848,800
Contractor
Location
Bid Total

1. Dominguez General Engineering.

Pomona
$770,560

2. Stephen Doreck Equipment Rentals, Inc.

Pico Rivera
$786,325

3. Big Ben Engineering Inc.

Irvine
$842,350

4. All Cities Engineering
Ontario
$847,350

5. T.E. Roberts Inc.

Irvine
$889,579

6. Bonadiman Water Inc.

Perris
$927,525

7. CEM Construction Corp
Montebello
$998,750

8. Palp, Inc. DBA Excel Paving
Long Beach
$1,040,440

9. American Pipeline Services
Monrovia
$1,096,685

10. GCI Construction
San Clemente
$1,461,750