ATTACHMENT 1 – BUDGET DATA SHEET
FULLERTON FLIGHT CENTER RENNOVATION PROJECT
Project No.: 49016
Source of Funds
Existing Budget:
Airport Enterprise Fund $673,039
Private Donation $2,300,000
Proposed Budget Transfers:
Airport Enterprise Fund Loan Proceeds to Project 49016 $1,300,000 TOTAL $4,273,039
Estimated Expenditures
Project Design - Consultants $195,199
Staff Design, Administration and Processing $25,000
Building Purchase Cost $1,300,000
Construction Contract $2,360,527
Estimated Surveying, Inspection, Testing,
and Contract Administration (6.5%) $151,159
Contingencies (10%) $232,553
TOTAL $4,264,418
Summary of Bids
Bid Opening: January 17, 2024
Engineer’s Estimate: $2,200,000
Contractor
Location
Base Bid*
Bid Alt B
1. SS+K Construction Inc
Mission Viejo
$2,325,527
$35,000
2. Tovey/Shultz Construction Inc
Lake Elsinore
$2,444,301
$45,460
3. FAR Electric, Inc DBA Far Builders
Anaheim
$2,499,316
$73,450
4. Monet Construction Inc
Tujunga
$2,710,505
$60,000
5. Caliba Inc
Stanton
$2,723,000
$76,000
6. CALTEC Corp
Westminster
$2,820,000
$90,000
7. Facility Builders and Erectors
Anaheim
$2,879,339
$53,502
8. DF Perez Construction Inc
Anaheim
$2,917,033
$23,125
9. DC Integrate, Inc
City of Industry
$3,067,000
$62,000
10. Newman Midland Corp
Long Beach
$3,363,750
$100,000
11. BCM Group, Inc
Rancho Cucamonga
$4,250,000
$0
*Project awarded on base bid cost.