ATTACHMENT 1 – BUDGET DATA SHEET
RESIDENTIAL STREET REHABILITATION – VARIOUS LOCATIONS FY 2023-24 Project No.: 44067
Source of Funds
Existing Budget:

ARPA Revenue Replacement Funds $50,000
Proposed Budget Transfers:

ARPA Revenue Replacement Funds from Project 44589 $1,173,000 TOTAL $1,223,000
Estimated Expenditures
Staff Design, Administration and Processing $42,000
Construction Contract $980,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $98,000
Tree Removals $5,000
Contingencies (10%) $98,000
TOTAL $1,223,000
Summary of Bids
Bid Opening: February 22, 2024
Engineer’s Estimate: $1,035,000
Contractor
Location
Bid Total

1. Hardy & Harper, Inc.

Lake Forest
$980,000

2. Onyx Paving Company, Inc.

Anaheim
$1,011,000

3. Sequel Contractors, Inc.

Santa Fe Springs
$1,034,930

4. All American Asphalt
Corona
$1,047,000

5. RJ Noble Company
Orange
$1,118,740

6. Palp, Inc. DBA Excel Paving Company
Long Beach
$1,126,664