ATTACHMENT 1 – BUDGET DATA SHEET
MISCELLANEOUS SEWER LINING PROJECT FY 2023-24
Project No.: 51357
Source of Funds
Existing Budget:
Sewer Enterprise Fund $15,000
Proposed Budget Transfers:
Sewer Enterprise Fund from Project 51419 $395,000
TOTAL $410,000
Estimated Expenditures
Staff Design, Administration and Processing $8,000
Construction Contract $287,135
Estimated Surveying, Inspection, Testing,
and Contract Administration (10.0%) $28,714
Contingencies $86,140
TOTAL $401,989
Summary of Bids
Bid Opening: February 26, 2024
Engineer’s Estimate: $439,000
Contractor
Location
Bid Total
1. Insituform Technologies, Inc.
Chesterfield, MO
$287,135
2. Sancon Technologies, Inc.
Huntington Beach
$374,620
3. Bonadiman Water, Inc.
Riverside
$449,150
4. DownStream Services Inc.
Escondido
$524,079