ROAD MAINTANANCE AND REHABILITATION ACCOUNT (RMRA)/ SENATE BILL 1 (SB1) RESOLUTION APRIL 16, 2024
SB1 FUNDS ALLOCATION
Background
Senate Bill 1 (SB 1), known as the Road Repair and Accountability Act (RMRA) of 2017.
Intent is to address/fund basic roadway maintenance, rehabilitation and critical safety needs.
RMRA revenues are the result of increases in the fuel excise taxes, diesel fuel sales taxes and vehicle registration fees.
We have programmed and completed projects since 2018 using SB1 funds.
Expected SB 1 funding for FY 2024-25 is approximately $3.7 million.
Previous SB1 Projects
3 FY 2017-18
Project 1 - Chapman Avenue (Acacia Ave to SR-57)
FY 2018-19
Project 2 - Commonwealth Avenue (Balcom Ave to Montegue Ave) Raymond Avenue (Commonwealth Ave to Chapman Ave)
FY 2019-20
Project 3 - Euclid Street (Williamson Ave to Fern Dr)
FY 2020-21
Project 4A - Euclid Street (Fern Dr to Bastanchury Rd) & Valley View Pl Project 4B - Orangethorpe Avenue (Woods Ave to Highland Ave) FY 2021-22
Project 5A – Rosecrans Avenue (City Limits to Sunny Ridge) Project 5B - Valencia Avenue (Magnolia Ave to Gilbert St) FY 2022-23
Project 6A – Associated Road (Rolling Hills to Imperial Hwy) Project 6B - Orangethorpe Avenue (State College to Placentia Ave) FY 2023-24
Project 7A – State College Blvd (Yorba Linda Blvd to City Limits) Project 7B – Slurry Seal (Various Residential Streets)
Funding Requirements
To receive funds, the California State Commission (CTC) requires City submit a list of proposed projects utilizing SB1 revenue by July 1, 2024.
CTC submittal requirements include:
Public review of proposed projects.
Infrastructure and Natural Resources Advisory Committee (INRAC) reviewed and supported the project at their March 18, 2024 meeting.
Use of Pavement Management Plan (PMP) to develop the list of potential projects.
City Council approval of Resolution identifying the list of projects.
Potential Arterial Street Projects
5 Project 1 – Gilbert Street
Valencia Ave to Commonwealth Ave
Project 2 – Rosecrans Avenue
Camino Centraloma to Parks Rd
Project 3 – Malvern Ave
Bastanchury Rd to Basque Ave
Project 4 – Euclid St at SR-91
SR-91 Interchange
Project 5 – Valencia Avenue
Euclid St to Woods Ave
Project 6 - Harbor Boulevard
SR-19 to Chapman Ave
Project 7 - Harbor Boulevard
Chapman Ave to Berkeley Ave
Project 8 – Raymond Avenue – joint project with Anaheim SR-91 to Orangethorpe Ave
Project 9 – Acacia Avenue
City Limits to Orangethorpe Ave
Project 10 – Commonwealth Avenue
State College Blvd to Chapman Ave
Project 11 – Commonwealth Avenue
Acacia Ave to State College Blvd
Project 12 – Yorba Linda Boulevard
Associated Rd to Placentia Ave
Projects 2, 5, 10, 11 are not recommended at this time as they are programmed for future water main replacement
Potential Local Street Projects
6 Project 1 – Las Palmas Area – Phase 2
Project 2 – Sunny Hills Area
Project 3 – Conejo Lane Area
Project 4 – Panorama Road Area
Project 5 – Courtney Avenue Area
Project 6 – Maxim Avenue Area
Project 7 – Acacia Avenue-Nutwood Avenue
Project 8 – Hartford Avenue Area
Preferred Project(s): 3, 5, 6, or 7
Projects 3 and 7 are adjacent to school sites
Projects 5 & 6 have adjacent streets in good condition
Staff Recommended SB1 Project
7 MAPLEWOOD AREA
Including portion of Valencia Ave
Estimated Construction Cost = $3.1M
Estimated Total Project Cost = $3.7M
Pavement Rehabilitation (assumed)
3” Grind & Overlay (Valencia)
4” Grind & Overlay (Residentials)
Concrete curb ramps, curb & gutter repair, sidewalk repair, driveway repair as needed A separate water main replacement project covers much of the Project area.
Recommendation
Adopt the proposed Resolution Listing Maplewood Area for pavement rehabilitation for Fiscal Year 2024-25 funded by SB1, the Road Repair and Accountability Act of 2017.