ATTACHMENT 1 - BUDGET DATA SHEET
CANDLEWOOD AREA WATER MAIN
REPLACEMENT PROJECT NO. 53054
Source of Funds
Existing Budget:
Water Fund $90,000
Proposed Budget Transfers:
Water Fund from Project 53250 $1,460,000
TOTAL $1,550,000
Estimated Expenditures
Project Design $55,000
Construction Contract $1,298,246
Estimated Surveying, Inspection, Testing, 5.0% $65,000
and Contract Administration
Contingencies 10.0% $130,000
TOTAL $1,548,246
Summary of Bids
Bid Opening: May 6th, 2024
Engineer's Estimate: $1,606,750
Contractor Location Bid Total
1. Williams Pipeline Contractors, Inc. Mission Hills, CA $1,298,246.00
2. All Cities Engineering, Inc. Ontario, CA $1,350,460.00
3. Dominguez General Engineering Inc. Pomona, CA $1,478,398.00
4. Big Ben Engineering. Irvine, CA $1,517,328.00
5. Vido Samarzich, Inc. Rancho Cucamonga, CA $1,578,060.00
6. CEM Construction Corp Montebello, CA $1,585,910.00
7. GCI Construction, Inc. San Clemente, CA *$1,828,808.00
8. American Pipeline Services Monrovia, CA **$1,880,580.00
9. JA Salazar Construction La Habra, CA $1,915,860.00
10. R.E Chaffee Construction Wrightwood, CA $2,851,560.00
*= Submitted bid amount was $1,902,608.00, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $1,828,808 **= Submitted bid amount was $1,881,180.00, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $1,880,580.00.