Source of Funds
Existing Budget:
Water Fund $80,000
Proposed Budget Transfers:
Water Fund from Project 53250 $1,455,000
TOTAL $1,535,000
Estimated Expenditures
Construction Contract $1,288,690
Project Design $52,000
Estimated Surveying, Inspection, Testing, 5.0% $65,000
and Contract Administration
Contingencies 10.0% $129,000
TOTAL $1,534,690
Bid Opening: May 1
st, 2024
Engineer's Estimate: $1,670,000
Contractor Location Bid Total
1. Big Ben, Inc. Irvine, CA $1,288,690.00
2. Williams Pipeline Contractors, Inc. Rancho Cucamonga, CA $1,451,000.00
3. Dominguez General Engineering Inc. Pomona, CA $1,453,950.00
4. All Cities Engineering, Inc. Corona, CA *$1,478,600.00
5. CEM Construction Corporation Riverside, CA $1,514,550.00
6. Vido Samarzich, Inc. Rancho Cucamonga, CA $1,598,000.00
7. T.E. Roberts, Inc. Montebello, CA $1,822,148.00
*= Submitted bid amount was $1,478,100.00, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $1,478,600.00.
ATTACHMENT 1 - BUDGET DATA SHEET
FIRETHORNE AREA WATER MAIN REPLACEMENT
PROJECT NO. 53044
Summary of Bids