ATTACHMENT 1 – BUDGET DATA SHEET
MISCELLANEOUS SLURRY SEAL FY23-24 PROJECT
Project No.: 44699
Source of Funds
Proposed Budget Transfers:

RMRA/SB1 Funds from Project 44589 $600,000
General Funds from Project 44589 $400,000
TOTAL $1,000,000
Estimated Expenditures
Staff Design, Administration and Processing $15,000
Construction Contract $820,596
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $82,060
Contingencies (10%) $82,060
TOTAL $999,716
Summary of Bids
Bid Opening: June 5, 2024
Engineer’s Estimate: $826,997
Contractor
Location
Bid Total

1. Roy Allan Slurry Seal, Inc.

Santa Fe Springs
$820,596

2. Pavement Coatings Co.

Jurupa Valley
$838,721

3. American Asphalt South
Riverside
$888,471

4. All American Asphalt
Corona
$998,334