ATTACHMENT 1 – BUDGET DATA SHEET
SUNNY HILLS-TWILIGHT AREA WATER MAIN REPLACEMENT
Project No.: 53039
Source of Funds
Existing Budget:
Water Fund $130,000
Proposed Budget Transfers:
Water Fund from Project 53250 $4,100,000
TOTAL $4,230,000
Estimated Expenditures
Project Design - Consultants $99,745
Staff Design, Administration and Processing $10,000
Construction Contract $3,668,775
Estimated Surveying, Inspection, Testing,
and Contract Administration (5%) $183,439
Contingencies (5%) $183,439
TOTAL $4,145,398
Summary of Bids
Bid Opening: May 25, 2024
Engineer’s Estimate: $6,282,919
Contractor
Location
Bid Total
1. Big Ben Inc.
Irvine
$3,668,775
2. All Cities Engineering, Inc.
Ontario
$4,349,900
3. Dominguez General Engineering, Inc.
Pomona
$4,351,000
4. CEM Construction Corporation
Montebello
$4,396,380
5. Williams Pipeline Contractors, Inc.
Mission Hills
$4,467,400
6. J.A. Salazar Construction
La Habra
$4,643,900
7. Vido Samarzich, Inc.
Rancho Cucamonga
$4,778,750
8. T.E. Roberts, Inc
Irvine
$5,204,447
9. Bonadiman Water, Inc.
Perris
$5,317,550
10. Kana Pipeline, Inc.
Riverside
$6,192,960
11. Gentry General Engineering, Inc.
Colton
$7,872,053