ATTACHMENT 1 – BUDGET DATA SHEET
Traffic Signal Modification at Euclid St and Rosecrans Ave Project No.: 46991
Source of Funds
Existing Budget:
Measure M2 from Project 46621 $50,000
Proposed Budget Transfers:
Measure M2 from Project 46621 $600,000
TOTAL $650,000
Estimated Expenditures
Staff Design, Administration and Processing $30,000
Construction Contract $516,888
Estimated Inspection and Contract Admin $15,000
Contingencies (15%) $82,784
TOTAL $644,672
Summary of Bids
Bid Opening: August 29, 2024
Engineer’s Estimate: $401,000
Contractor
Location
Base Bid Total
1. High Light Electric Inc.
Colton
$516,888
2. Calpromax Engineering Inc
Placentia
$569,000
3. Crosstown Electrical
Irwindale
$588,954
4. Elecno Belco
Chino
$589,261
5. DBX Inc
Temecula
$806,622