ID Task Name Duration Start Finish Predecessors Work Cost 1 City of Fullerton - SCADA Planning and Assessment Services260 days Mon 11/18/24Wed 11/26/25 1,109.53 hrs$410,680.50 2 Key Milestones 240 days Mon 11/18/24Wed 10/29/25 0 hrs $0.00 3 Notice to Proceed 0 days Mon 11/18/24Mon 11/18/24 0 hrs $0.00 4 City Response to RFI 2 wks Fri 12/13/24Fri 12/27/249 0 hrs $0.00 5 Project Completion 0 days Wed 10/29/25Wed 10/29/2555FF 0 hrs $0.00 6 Task 1 - Kickoff Meeting (and Project Management)260 days Mon 11/18/24Wed 11/26/25 199 hrs$49,345.32 7 Internal Kickoff Meeting 1 day Mon 11/25/24Mon 11/25/243FS+1 wk 5 hrs $1,418.00 8 External Kickoff Meeting 1 day Thu 12/5/24Thu 12/5/247FS+1 wk 16 hrs $6,368.00 9 Issue RFI 1 wk Fri 12/6/24 Thu 12/12/248 6 hrs $1,282.00 10 Project Management 260 days Mon 11/18/24Wed 11/26/25 160 hrs$37,610.76 11 Start Date 0 days Mon 11/18/24Mon 11/18/243SS 0 hrs $0.00 12 End Date 0 days Wed 11/26/25Wed 11/26/2513 0 hrs $0.00 13 Project Closeout 1 mon Thu 10/30/25Wed 11/26/2555 12 hrs $2,666.56 14 Task 2 - Review of Draft SCADA Master Plan21 days Mon 12/30/24Tue 1/28/25 81 hrs$19,633.28 15 Review of SCADA Master Plan and RRA 2 wks Mon 12/30/24Mon 1/13/254 56 hrs$13,663.68 16 Cybersecurity Assessment Update 11 days Tue 1/14/25Tue 1/28/25 25 hrs $5,969.60 17 Cyber Workshop 1 day Tue 1/14/25 Tue 1/14/2515 9 hrs $2,414.88 18 Draft Cyber TM 10 days Wed 1/15/25Tue 1/28/25 16 hrs $3,554.72 19 Development 1 wk Wed 1/15/25Tue 1/21/2517 8 hrs $1,555.84 20 QA/QC 2 days Wed 1/22/25Thu 1/23/2519 2 hrs $665.60
21 Incorporate Comments 2 days Fri 1/24/25 Mon 1/27/2520 4 hrs $777.92 22 Submit to City Staff 1 day Tue 1/28/25 Tue 1/28/2521 2 hrs $555.36 23 Task 3 - Data Gathering, Site Visits, and Staff Interviews44 days Wed 1/29/25Tue 4/1/25 204 hrs$54,128.84 24 Site Visits and Staff Interviews 3 days Wed 1/29/25Fri 1/31/25 14 68 hrs$19,912.84 25 Review of Existing Documentation (excluding Draft
SCADA Master Plan and RRA)
2 wks Mon 2/3/25 Fri 2/14/25 24 60 hrs$14,435.20
26 Baseline Assessment and Gap Analysis 31 days Tue 2/18/25Tue 4/1/25 76 hrs$19,780.80 27 Development 3 wks Tue 2/18/25 Mon 3/10/2525 56 hrs$13,769.60 28 QA/QC 1 wk Tue 3/18/25 Mon 3/24/2527,78 4 hrs $1,460.16 29 Incorporate Comments 1 wk Tue 3/25/25 Mon 3/31/2528 12 hrs $3,440.32 30 Submit to City Staff 1 day Tue 4/1/25 Tue 4/1/25 29 4 hrs $1,110.72 31 Task 4 - Condition Assessment and Recommended
Software and Network Upgrades
96 days Tue 3/11/25Thu 7/24/25 236 hrs$104,685.60
32 Condition Assessment 2 wks Tue 3/11/25 Mon 3/24/2527 32 hrs $7,105.28 33 Wireless Study 4 wks Tue 3/11/25 Mon 4/7/2532SS 0 hrs $45,000.00 34 Alternatives Evaluation 20 days Thu 4/24/25Wed 5/21/25 84 hrs$21,596.64 35 Development 3 wks Thu 4/24/25Wed 5/14/2533FF,75 68 hrs$17,534.40 36 QA/QC 2 days Thu 5/15/25Fri 5/16/25 35 2 hrs $730.08 11/18
10/29
11/18
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress

Page 1 ends

Project: City of Fullerton - SCAD
Date: Tue 10/1/24
ID Task Name Duration Start Finish Predecessors Work Cost 37 Incorporate Comments 2 days Mon 5/19/25Tue 5/20/2536 10 hrs $2,221.44 38 Submit to City Staff 1 day Wed 5/21/25Wed 5/21/2537 4 hrs $1,110.72 39 Recommendations 28 days Mon 6/16/25Thu 7/24/25 120 hrs$30,983.68 40 Development 4 wks Mon 6/16/25Mon 7/14/2579 80 hrs$20,200.96 41 QA/QC 2 days Tue 7/15/25 Wed 7/16/2540 4 hrs $1,460.16 42 Incorporate Comments 1 wk Thu 7/17/25Wed 7/23/2541 32 hrs $8,211.84 43 Submit to City Staff 1 day Thu 7/24/25Thu 7/24/2542 4 hrs $1,110.72 44 Task 5 - Initial Workshop with City Staff (and
Preliminary Conceptual Incremental Implementation
Plan Development)
58 days Fri 8/8/25 Wed 10/29/25 155 hrs$37,876.80
45 Recommendations Review Workshop 1 day Fri 8/8/25 Fri 8/8/25 43FS+2 wks 12 hrs $2,997.28 46 Incorporate City Comments in Recommendations2 wks Mon 8/11/25Fri 8/22/25 45 28 hrs $6,884.80 47 Preliminary Conceptual Incremental Implementation
Plan
47 days Mon 8/25/25Wed 10/29/25 115 hrs$27,994.72
48 Draft Plan 26 days Mon 8/25/25Tue 9/30/25 74 hrs$18,360.16 49 Development 3 wks Mon 8/25/25Mon 9/15/2546 52 hrs$12,217.92 50 QA/QC 1 wk Tue 9/16/25 Mon 9/22/2549 8 hrs $2,920.32 51 Incorporate Comments 1 wk Tue 9/23/25 Mon 9/29/2550 12 hrs $2,666.56 52 Submit to City Staff 1 day Tue 9/30/25 Tue 9/30/2551 2 hrs $555.36 53 Implementation Plan Review Workshop1 day Wed 10/15/25Wed 10/15/2552FS+2 wks 17 hrs $4,301.44 54 Final Plan 10 days Thu 10/16/25Wed 10/29/25 24 hrs $5,333.12 55 Incorporate City Comments/Finalize 2 wks Thu 10/16/25Wed 10/29/2553 24 hrs $5,333.12 56 Task 6 - Miscellaneous Items 240 days Mon 11/18/24Wed 10/29/25 234.53 hrs$145,010.66 57 Task 6.1 - O&M Training 240 days Mon 11/18/24Wed 10/29/25 142.53 hrs$38,605.20 61 Task 6.2 - Coordination with Third-Party Vendors240 days Mon 11/18/24Wed 10/29/25 24 hrs $4,861.14 65 Task 6.3 - Grant Applications and Administration
Support
240 days Mon 11/18/24Wed 10/29/25 0 hrs $5,000.00
69 Task 6.4 - Electrical, Instrumentation, and Controls (EI&C) Support
240 days Mon 11/18/24Wed 10/29/25 0 hrs $5,000.00
73 Task 6.5 - Optional Tasks 99 days Mon 2/3/25Mon 6/23/25 68 hrs$56,544.32 74 Task 6.5.1 - As-Is Roles and Responsibilities
Definition (OPTIONAL)
1 day Tue 2/25/25Tue 2/25/2527SS+1 wk 10 hrs $2,387.84
75 Task 6.5.2 - Baseline Assessment Review
Workshop (OPTIONAL)
6 days Wed 4/16/25Wed 4/23/25 24 hrs $5,884.32
78 Task 6.5.3 - "A Day Without SCADA" Tabletop
Exercise (OPTIONAL)
6 wks Mon 2/3/25Mon 3/17/2525SS 0 hrs $40,000.00
79 Task 6.5.4 - Alternatives Evaluation Review
Workshop (OPTIONAL)
6 days Fri 6/6/25 Fri 6/13/25 24 hrs $5,884.32
82 Task 6.5.5 - To-Be Roles and Responsibilities
Definition (OPTIONAL)
1 day Mon 6/23/25Mon 6/23/2540SS+1 wk 10 hrs $2,387.84
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress

Page 2 ends

Project: City of Fullerton - SCAD
Date: Tue 10/1/24
ID Task Name Duration Start Finish Predecessors Work Cost 83 Task 6.6 - As-Needed Services (OPTIONAL)240 days Mon 11/18/24Wed 10/29/25 0 hrs $35,000.00 Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress

Page 3 ends

Project: City of Fullerton - SCAD
Date: Tue 10/1/24