BID SCHEDULE

EMERY PARK PLAYGROUND RENOVATION
PROJECT NO. 54045

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 MOBILIZATION 1 LS $8,000 $8,000.00
2 CLEAR AND GRUB 1 LS $23,000 $23,000.00
3 WATER POLLUTION CONTROL 1 LS $20,000 $20,000.00
4 DEMOLITION AND REMOVALS 1 LS $42,000 $42,000.00
5 SITE EXCAVATION & GRADING 1 LS $25,000 $25,000.00
6 SIDEWALK 4000 SF $16 $64,000.00
7 DRIVEWAY 260 SF $42 $10,920.00
8 PLAY PIT PCC CURB EDGE 255 LF $75 $19,125.00
9 PCC MOW CURB 55 LF $90 $4,950.00
10 6" PCC CURB 35 LF $95 $3,325.00
11 PCC DRAINAGE GUTTER 150 LF $45 $6,750.00
12 PLAY PIT ACCESSIBLE RAMP 150 SF $49 $7,350.00
13 PLAY PIT DRAINAGE SYSTEM 1 LS $12,000 $12,000.00
14 BLOCK WALL 140 LF $225 $31,500.00
15 SITE AMENITIES 1 LS $26,000 $26,000.00
16 MONUMENT SIGN 1 EA $35,000 $35,000.00
17 SITE IRRIGATION 1 LS $25,000 $25,000.00
18 SITE LANDSCAPE 1 LS $30,000 $30,000.00
Base Bid Total $ 393,920.00
Additive Bid Alternate 'A'
A1 DEMOLITION AND REMOVALS 1 LS $5,000 $5,000.00
A2 SITE EXCAVATION & GRADING 1 LS $5,000 $5,000.00
A3 TRAFFIC CONTROL 1 LS $3,000 $3,000.00

TO BE SUBMITTED WITH BID
BD-14

BID SCHEDULE

EMERY PARK PLAYGROUND RENOVATION
PROJECT NO. 64045

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
A4 SIDEWALK 1110 $18.50 $20,535.00
A5 ADA RAMP 1 EA $12,000 $12,000.00
AG 8" PCC CURB 30 LF $210 $6,300.00
A7 6" VEHICULAR CONCRETE PAD 550 SF $24 $13,200.00
A8 STAMPED CONCRETE 120 SF $35 $4,200.00
A9 STREET LIGHTING CONDUIT 100 LF $30 $3,000.00
Bid Alternate 'A' Total $ 72,235.00
Unit prices are required for all bid items.

The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award.

Changes to either Unit Price or Amount shall be striked-out and initialed items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.

If the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company Aguilar & Calderon Corp.

Name Marion Calderon
Signature Martif
Address PO BOX 1511
City & Zip Code Whittier, CA 90609
Phone Number 562-265-8815
License Number 988688