BID SCHEDULE

CANNON / SHEPPARD AREA WATER MAIN REPLACMENT
PROJECT NO. 53043

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS $60,000 $60,000
2 Water Pollution Control 1 LS $5,000 $5,000
3 Traffic Control 1 LS $12,000 $12,000
4 Sheeting, Shoring and Bracing 1 LS $5,000 $5,000
5 Construct 12" PVC Water Pipe 1,000 LF $165 $165,000
6 Construct 10" PVC Water Pipe 20 LF $300 $6,000
7 Construct 8" PVC Water Pipe 4,060 LF $130 $527,800
8 Construct 6" PVC Water Pipe 60 LF $400 $24,000
9 Construct 4" PVC Water Pipe 60 LF $240 $14,400
10 Construct 12" Water Gate Valves 4 EA $5,000 $20,000
11 Construct 10" Water Gate Valves 1 EA $4,200 $4,200
12 Construct 8" Water Gate Valves 13 EA $3,000 $39,000
13 Construct 6" Water Gate Valves 2 EA $2,800 $5,600
14 Construct 4" Water Gate Valves 1 EA $2,000 $2,000
15 Construct 1" Water Services 89 EA $2,500 $222,500
16 Construct 2" Water Services EA $8,000 $24,000
17 Construct Fire Hydrant Assemblies - Standard 10 EA $14,000 $140,000 18 Remove Existing Fire Hydrants 10 EA $1,000 $10,000
19 Construct 8" Utility Undercrossing 75 LF $180 $13,500 20 Construct 12" Utility Undercrossing 125 LF $200 $25,000 21 Construct 2" Blow-Off Assemblies 2 EA $7,000 $14,000 22 Construct 1" Combination Air Release Valve 6 EA $6,000 $36,000 Assemblies
23 Abandon Valve Boxes 33 EA $300 $9,900

TO BE SUBMITTEO WITH BID

BID SCHEDULE

CANNON / SHEPPARD AREA WATER MAIN REPLACMENT
PROJECT NO. 53043

ESTIMATED

NO ITEM QUANTITY UNIT UNIT PRICE AMOUNT
24 Remove Abandoned Waterline in the Same Trench 100 LF $50 $5,000 Demolish and Reconstruct Curb and Gutter 5 LF
25 $300 $1,500
(6" Curb Face)
26 Demolish and Reconstruct Sidewalks 400 SF $40 $16,000 27 Remove and Reconstruct Decorative Masonry 1 LS $2,000 $2,000 |(1135 Sheppard Drive)
Remove and Reconstruct Concrete Driveway 1 LS $10,000
28 $10,000
|(1224 Frances Avenue)
Waterline Trench Pavement Repair 1,100 TON $350 $385,000 29 |(0.5-ft. Thickness)
Base Bid Total $ $1,804,400.00
Unit prices are required for all bid items.

The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award.

Changes to either Unit Price or Amount shall be striked-out and initialed Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.
if the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company WILLIAMS PIPELINE CONTRACTORS, INC
Name Victor Hernandez
Signature 441
Address 10200 SEPULVEDA BLVD STE 255
City & Zip Code_ MISSION HILLS, CA 91345
Phone Number 805-386-2393
License Number 353528