ATTACHMENT 1 – BUDGET DATA SHEET
S. RAYMOND AVENUE CUL-DE-SACS INFRASTRUCTURE IMPROVEMENTS Project No.: 53048
Source of Funds
Existing Budget:
Water Fund $50,000
Sewer Enterprise Fund $25,000
Proposed Budget Transfers:
Water Fund from Project 53250 $1,814,000
Sewer Enterprise Fund from Project 51419 $636,000
TOTAL $2,525,000
Estimated Expenditures
Construction Contract $1,931,120
Staff Design, Administration and Processing $110,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $193,112
Contingencies (15%) $289,668
TOTAL $2,523,900
Summary of Bids
Bid Opening: January 30, 2025
Engineer’s Estimate: $2,460,000
Contractor
Location
Bid Total
1. Dominguez General Engineering Inc.
Pomona, CA
$1,931,120
2. Big Ben, Inc.
Irvine, CA
$2,492,160
3. Stephen Doreck Equipment Rentals, Inc.
Pico Rivera, CA
$2,529,035
4. Romona, Inc.
Baldwin Park, CA
$2,560,950
5. CEM Construction Corporation
Montebello, CA
$2,591,525
6. Armstrong Cal Builders Inc.
Stanton, CA
$2,623,787
7. Excel Paving
Long Beach, CA
$2,755,675
8. Williams Pipeline Contractors, Inc.
Mission Hills, CA
$3,088,700