Cities Index.
040125 PW 2023 OCCSP Grant Acceptance Award Letter

City Council - Successor Agency - Housing Authority
April 1, 2025

Document
040125 PW 2023 OCCSP Grant Acceptance Award Letter
Meeting
April 1, 2025
Body
City Council - Successor Agency - Housing Authority
Pages
2
Original file
194 KB
Text extracted from the city's file for reading and search. Open the original on fullerton.legistar1.com. That file is the official record.

AFFILIATED AGENCIES

Orange County
Transit District

Local Transportation
Authority

Service Authority for
Freeway Emergencies

Consolidated Transportation
Service Agency

Congestion Management
Agency

Orange County Transportation Authority
550 South Main Street / P.O Box 14184 / Orange / California 92863-1584 / (714) 560-OCTA (6282) November 7, 2024

Mr. Stephen Bise
Public Works Director
City of Fullerton
303 W. Commonwealth Avenue
Fullerton, CA 92832

Subject: 2023 Orange County Complete Streets Program Award

Dear Mr. Bise,

Congratulations, funding is now available for your application for a complete street project. On February 12, 2024, the O range County Transportation Authority (OCTA) Board of Directors (Board) approved the 2023 Orange County Complete Streets Program (OCCSP) Project Prioritization Recommendations which awarded Surface Transportation Block Grant (STBG) and Congestion Mitigation and Air Quality Improvement (CMAQ) funds to Orange County projects and established a contingency list of projects.

On June 6, 2024, the Southern California Association of Governments Regional Council approved a contingency list which included nine projects, referred to by OCTA as Wave 3. OCTA has worked with SCAG to identify funding and th ose projects. This letter serves as a formal notification that the nine projects in Wave 3 of the OCCSP have been awarded CMAQ and/or STBG funds.

Awarded projects may now request authorization (RFA) of the federal funds through California Department of Transportation District 12 Local Assistance.

The OCCSP guidelines require that the project sponsor submit the documents required for the RFA no later than February of the federal fiscal year programmed. Requests submitted after February may risk losing the funds.

Please coordinate immediately with your respective Caltrans District Local Assistance Area Engineer for federal-aid project delivery.

Mr. Stephen Bise
November 7, 2024

Page 2 ends

Orange County Transportation Authority
550 South Main Street / P.O Box 14184 / Orange / California 92863-1584 / (714) 560-OCTA (6282) OCTA looks forward to supporting OCCSP projects through delivery and implementation and appreciates your interest in the program. Should you have any questions or need any assistance with the federal funding process , please contact Louis Zhao at (714) 560-5494 or [email protected].

Sincerely,

Kia Mortazavi, Executive Director
Planning

KM:vm
Attachments

c: Rose Casey, OCTA