Agency Project FTIP ID
FTIP Approved - Submit Request for Authorization
to Caltrans as soon as possible Phase of Work
Detailed Phase
of Work Fiscal Year
CMAQ
($000's)
STBG
($000's)
Total Funding
Request
($000's)
Total
Matching
Funds
($000's)
Total
Project Cost
($000's)
Anaheim Nohl Ranch Open Space Trail ORA152211 FTIP#23-20 approved on 1/05/2024. CON CON FY2024-25 $ - $ 3,359 3,359$ 459 $ 3,818$ Brea Tracks at Brea - Western Extension ORA190906 FTIP#23-25 approved on 4/17/2024. CON CON FY2025-26 $ 1,320 $ - 1,320$ 180 $ 5,730$ Costa Mesa
Adams Avenue Bicycle Facility Project –Harbor Boulevard to Fairview Road ORA230804 FTIP#23-25 approved on 4/17/2024. CON CON FY2024-25 $ - $ 1,760 1,760 $ 240 $ 2,000$ PE PS&E FY2024-25 $ - $ 176 CON CON FY2025-26 $ - $ 1,759 Costa Mesa Adams Avenue Active Transportation Project – Multipurpose Trails ORA230811 FTIP#23-20 approved on 1/05/2024. CON CON FY20 25-26 $ - $ 4,223 4,223$ 1,677 $ 6,413$ PA&ED FY2024-25 $ 140 $ - PS&E FY2025-26 $ - $ 580 CON CON FY2026-27 $ 4,278 $ - Orange PLAN - Citywide Active Transportation Plan ORA230806 FTIP#23-20 approved on 1/05/2024. CON (NI) CON (NI) FY2024-25 $ - $ 308 308$ 42 $ 350$ PE PS&E FY2024-25 $ 272 $ - CON CON FY2025-26 $ - $ 2,481 PA&ED FY2024-25 $ - $ 44 PS&E FY2025-26 $ - $ 132 CON CON FY2025-26 $ - $ 792 PE PA&ED FY2024-25 $ - $ 352 ROW ROW FY2025-26 $ - $ 660 CON CON FY2025-26 $ 2,416 $ - 8,426$ 16,626 $ 25,052 $ 4,533 $ 40,905 $ Agency Project FTIP ID
FTIP Approved - Submit Request for Authorization
to Caltrans as soon as possible Phase of Work
Detailed Phase
of Work Fiscal Year
CMAQ
($000's)
STBG
($000's)
Total Funding
Request
($000's)
Total
Matching
Funds
($000's)
Total
Project Cost
($000's)
Buena Park PLAN - Orangethorpe Avenue Complete Streets Planning Study ORA230806 FTIP #23-31 approved on 7/3/2024. CON (NI) CON (NI) FY2024-25 $ - $ 308 308 $ 42 $ 350$ PA&ED $ - $ 38
PS&E $ - $ 268
CON CON FY2025-26 $ - $ 4,548 PA&ED $ 4 $ -
PS&E $ 199 $ -
ROW ROW FY2025-26 $ 20 $ - CON CON FY2026-27 $ 3,793 $ 984 Irvine Venta Spur Trail and Jeffrey Road Pedestrian and Bicycle Bridge ORA230804 FTIP #23-31 approved on 7/3/2024. CON CON FY2026-27 $ 4,000 $ 1,000 5,000$ 1,000 $ 7,300$ PA&ED $ 396 $ -
PS&E $ 396 $ -
CON CON FY2027-28 $ 2,816 $ 704 PA&ED FY2024-25 $ - $ 273 PS&E FY2025-26 $ - $ 414 CON CON FY2026-27 $ - $ 2,728 PA&ED $ 1,241 $ -
PS&E $ 3,546 $ -
PE PS&E FY2024-25 $ 344 $ - CON CON FY2026-27 $ 1,783 $ 446 Tustin Main Street Enhancement Project ORA230804 FTIP #23-31 approved on 7/3/2024. CON CON FY2024-25 $ 802 $ 2,370 3,172$ 432 $ 3,604$ $ 19,340 $ 14,081 33,421$ 4,924 $ 40,072 $ Wave 1 Projects
Award approved through Orange County Transportation Authority (OCTA) Board of Directors as part of February 21, 2024 action. Projects are programmed in the FTIP.

Wave 2 Projects
Award approved through Southern California Association of Governments (SCAG) Regional Council as part of June 6, 2024 action. 968$ ORA230804 FTIP#23-25 approved on 4/17/2024.

Yorba Linda Connect Savi Ranch
Harbor Boulevard Complete Streets Improvement Project ORA230804 FTIP #23-31 approved on 7/3/2024. Pending
Amendment to the OCTA Master Plan of Arterial
Highways.

Complete Streets Along Avenida Calafia
ORA230804 FTIP#23-25 approved on 4/17/2024. 3,428$
TOTAL
Fullerton 4,854$
PE
PE FY2024-25
264$
2,199$
695$ 9,020$
377$ 3,130$
132$ 1,100$
467$ 7,145$
4,998$ Laguna Hills
Paseo De Valencia and Cabot Road Active Transportation
Enhancements ORA230810
FTIP#23-25 approved on 4/17/2024. Pending
Amendment to the OCTA Master Plan of Arterial
Highways.

Placentia Atwood Multi-Use Trail ORA190913 FTIP#23-20 approved on 1/05/2024.

PE
2,753$
FTIP #23-30 approved on 8/2/2024.
2,573$
Laguna Niguel
South Forbes Road/Oso Creek Trail Active Transportation Enhancements ORA230804 FTIP #23-31 approved on 7/3/2024.

Mission Viejo Mission Viejo Quad Cities Trail ORA233002 FTIP #23-30 approved on 8/2/2024. 5,000$
Orange Riverdale Avenue Complete Street Improvements ORA233301 FTIP #23-33 approved on 8/30/2024. Pending
Amendment to the OCTA Master Plan of Arterial
Highways.

PE
PE
PE
PE FY2024-25
FY2024-25
FY2024-25
Costa Mesa
Fairview Road Active Transportation Improvements – Adams Avenue to Fair Drive ORA230804 FTIP#23-25 approved on 4/17/2024. 1,935$ San Clemente
731$
5,731$
588$ 4,900$
465$ 3,880$
Huntington Beach
Irvine Harvard Avenue Complete Streets and Safety Improvements ORA230804 FTIP #23-31 approved on 7/3/2024. 4,312$ 3,415$
4,787$
TOTAL
Banning Avenue Roundabout & Southeast Corridors Complete Streets Improvements ORA233001
654$ 5,441$
351$ 2,998$
661$ 5,868$
Agency Project FTIP ID
FTIP Approved - Submit Request for Authorization
to Caltrans as soon as possible Phase of Work
Detailed Phase
of Work Fiscal Year
CMAQ
($000's)
STBG
($000's)
Total Funding
Request
($000's)
Total
Matching
Funds
($000's)
Total
Project Cost
($000's)
Buena Park PLAN - Stanton Avenue Complete Streets Planning Study ORA230806 FTIP #23-33 approved on 8/30/2024. CON (NI) CON (NI) FY202 5-26 $ - $ 308 308 $ 42 $ 350$ PA&ED FY2024-25 $ - $ 62 PS&E FY2025-26 $ - $ 88 CON CON FY2027-28 $ - $ 440 County of Orange
Los Patrones Parkway Bikeway Widening and Safety
Improvements ORA233308 FTIP #23-33 approved on 8/30/2024. CON CON FY2026-27 $ 2,764 $ - 2,764 $ 1,843 $ 4,607$ PA&ED $ 3 $ -
PS&E $ 158 $ -
ROW ROW FY2024-25 $ 16 $ - CON CON FY2025-26 $ - $ 3,794 Laguna Beach
Coast Highway Sidewalk Gap Closures to Achieve Complete Streets (Cardinal to 7th) ORA230804 FTIP #23-33 approved on 8/30/2024. CON CON FY2025-26 $ - $ 5,0 00 5,000$ 1,194 $ 7,275$ Los Alamitos
Los Alamitos Reimagine Downtown Street & Bicycle Corridor Improvement Project ORA230804 FTIP #23-33 approved on 8/30/2024. CON CON FY2025-26 $ 2,800 $ 2,200 5,000 $ 2,343 $ 7,343$ PE PS&E FY2024-25 $ 853 $ - ROW ROW FY2024-25 $ 583 $ - CON CON FY2025-26 $ 1,500 $ 1,968 PE PA&ED FY2024-25 $ - $ 31 ROW ROW FY2024-25 $ - $ 9 CON CON FY2025-26 $ - $ 3,228 PA&ED $ - $ 53
PS&E $ - $ 84
CON CON FY2025-26 $ - $ 374 8,677$ 17,639 $ 26,316 $ 7,309 $ 34,706 $ Agency Project FTIP ID
FTIP Approved - Submit Request for Authorization
to Caltrans as soon as possible Phase of Work
Detailed Phase
of Work Fiscal Year
CMAQ
($000's)
STBG
($000's)
Total Funding
Request
($000's)
Total
Matching
Funds
($000's)
Total
Project Cost
($000's)
PA&ED 3 $ - $
PS&E 157 $ - $
ROW ROW FY2025-26 16 $ - $
CON CON FY2026-27 3,899.4 $ 611.6 $
4,075.4$ 611.6 $ 4,687 $ 640 $ 5,327$ Wave 3 Projects
Award approved through SCAG Contingency List with grandfathered OCTA funds in fall 2024.

Stanton Orangewood Complete Streets ORA233304
FTIP #23-33 approved on 8/30/2024. Pending
Amendment to the OCTA Master Plan of Arterial
Highways. 3,268$
TOTAL
Yorba Linda Valley View Safety
Wave 4 Projects
Award approved through SCAG Contingency List with grandfathered OCTA funds in Spring 2025.

Huntington Beach Magnolia Street Corridor Complete Streets Improvements N/A TOTAL
PE
542$
FY2024-25
ORA230804 FTIP #23-33 approved on 8/30/2024. 70$
681$
513$
511$
Pending
PE FY2025-26
4,687$ 640 $
ORA230804 FTIP #23-33 approved on 8/30/2024. 590$
Huntington Beach Hamilton Avenue Corridor Complete Streets Improvements ORA230804 FTIP #23-33 approved on 8/30/2024. 3,971$ Orange Santiago Creek Bike Trail Gap Closure ORA230804 FTIP #23-33 approved on 8/30/2024. 4,904$ Brea Laurel Elementary School Safety
PE
PE FY2024-25
671$ 81$
581$
5,327$
4,513$
5,585$
3,781$
Agency Project FTIP ID Status Phase of Work
Detailed Phase
of Work Fiscal Year
CMAQ
($000's)
STBG
($000's)
Total Funding
Request
($000's)
Total
Matching
Funds
($000's)
Total
Project Cost
($000's)
PA&ED 308 $ - $
PS&E 387 $ - $
CON CON FY2026-27 2,262 $ 290 $
2,957$ 290 $ 3,247$ 443 $ 3,690$ Notes:

CMAQ - Congestion Mitigation and Air Quality Improvement Program Funds FTIP - Federal Transportation Improvement Program
MPAH - Master Plan of Arterial Highways
PA&ED - Project Approvals and Environmental Documentation PE - Preliminary Engineering
PS&E - Project Specifications and Estimates
ROW - Right-of-Way
CON - Construction
NI - Non Infrastructure
STBG - Surface Transportation Block Grant Program Funds Projects Remaining on SCAG Contingency List