ROAD MAINTANANCE AND REHABILITATION ACCOUNT (RMRA)/ SENATE BILL 1 (SB1) RESOLUTION APRIL 1, 2025
SB1 FUNDS ALLOCATION
Background
Senate Bill 1 (SB 1), known as the Road Repair and Accountability Act (RMRA) of 2017.
Intent is to address/fund basic roadway maintenance, rehabilitation and critical safety needs.
RMRA revenues are the result of increases in the fuel excise taxes, diesel fuel sales taxes and vehicle registration fees.
We have programmed and completed projects since 2018 using SB1 funds.
Expected SB 1 funding for FY 2025-26 is approximately $3.77 million.
Previous SB1 Projects
3 FY 2017-18
Project 1 - Chapman Avenue (Acacia Ave to SR-57)
FY 2018-19
Project 2 - Commonwealth Avenue (Balcom Ave to Montegue Ave) Raymond Avenue (Commonwealth Ave to Chapman Ave)
FY 2019-20
Project 3 - Euclid Street (Williamson Ave to Fern Dr)
FY 2020-21
Project 4A - Euclid Street (Fern Dr to Bastanchury Rd) & Valley View Pl Project 4B - Orangethorpe Avenue (Woods Ave to Highland Ave) FY 2021-22
Project 5A – Rosecrans Avenue (City Limits to Sunny Ridge) Project 5B - Valencia Avenue (Magnolia Ave to Gilbert St) FY 2022-23
Project 6A – Associated Road (Rolling Hills to Imperial Hwy) Project 6B - Orangethorpe Avenue (State College to Placentia Ave) FY 2023-24
Project 7A – State College Blvd (Yorba Linda Blvd to City Limits) Project 7B – Slurry Seal (Various Residential Streets)
FY 2024-25
Project 8 – Maplewood Area
Funding Requirements
To receive funds, the California Transportation Commission (CTC) requires City submit a list of proposed projects utilizing SB1 revenue by July 1, 2025.
CTC submittal requirements include:
Public review of proposed projects.
Infrastructure and Natural Resources Advisory Committee (INRAC) reviewed and supported the project at their February 24, 2025 meeting.
Use of Pavement Management Plan (PMP) to develop the list of potential projects.
City Council approval of Resolution identifying the list of projects.
Potential Arterial Street Projects
5 Project 1 – Rosecrans Avenue
Camino Centraloma to Camino Loma
Project 2 – Malvern Ave
Bastanchury Rd to Basque Ave
Project 3 – Euclid St at SR-91
SR-91 Interchange
Project 4 – Raymond Avenue – joint project with Anaheim SR-91 to Orangethorpe Ave
Project 5 – Acacia Avenue
City Limits to Orangethorpe Ave
Project 6 – Commonwealth Avenue
Montague Ave to State College Blvd
Project 7 – Commonwealth Avenue
State College Blvd to Chapman Ave
Project 8 – Yorba Linda Boulevard
Associated Rd to Placentia Ave
Projects 6 & 7 are not recommended at this time as they are programmed for future water main replacement
Potential Local Street Projects
6 Project 1 – Candlewood Area
Project 2 – Courtney Avenue Area
Project 3 – Rancho-Verona-Yucca Area
Project 4 – Sunny Hills-Twilight Area
Project 5 – Firethorne Area
Project 6 – Cannon-Sheppard Area
Project 5 is adjacent to a school site
Project 6 includes streets in good condition
Staff Recommended SB1 Project #1
7 SUNNY HILLS-TWILIGHT AREA
Residential Neighborhood
Estimated Total Project Cost = $2.5M
Pavement Rehabilitation
2” Grind & Overlay (expected)
Concrete curb ramps, curb & gutter repair, sidewalk repair, driveway repair.
Area recently completed a water main replacement project.
Staff Recommended SB1 Project #2
8 CANDLEWOOD AREA
Residential Neighborhood
Estimated Total Project Cost = $1.2M
Pavement Rehabilitation
2” Grind & Overlay (expected)
Concrete curb ramps, curb & gutter repair, sidewalk repair, driveway repair.
Area recently completed a water main replacement project.
Recommendation
Adopt the proposed Resolution listing Sunny Hills-Twilight Area and Candlewood Area for pavement rehabilitation for Fiscal Year 2025-26 funded by SB1, the Road Repair and Accountability Act of 2017.
Questions?