ATTACHMENT 1 – BUDGET DATA SHEET
AMERIGE AVENUE REHABILITATION PROJECT
Project No.: 44082
Source of Funds
Existing Budget:
General Fund $50,000
Proposed Budget Transfers:
General Fund from Project 44400 $375,000
TOTAL $425,000
Estimated Expenditures
Staff Design, Administration and Processing $30,000
Construction Contract $280,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (15%) $42,000
Tree Removals $30,000
Contingencies (15%) $42,000
TOTAL $424,000
Summary of Bids
Bid Opening: April 18, 2025
Engineer’s Estimate: $372,000.00
Contractor
Location
Bid Total
1. Hardy & Harper
Lake Forest
$280,000.00
2. RJ Noble
Orange
$288,021.00
3. All American Asphalt
Corona
$291,504.00
4. Sequel Contractors
Santa Fe Springs
$295,331.00
5. PALP, dba Excel Paving
Long Beach
$334,890.00
6. Calmex Engineering
Bloomington
$337,654.00
7. Towo Enterprise
Fullerton
$347,875.00
8. Vido Samarzich
Santa Ana
(1) $352,325.00
9. Big Ben Engineering
Irvine
$356,294.00
10. Estate Design and Construction
Los Angeles
(2) $358,876.33
11. Onyx Paving Company
Anaheim
$363,000.00
(1) = Submitted bid amount was $357,325, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $352,325. (2) = Submitted bid amount was $358,880, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $358,876.