ATTACHMENT 1 – BUDGET DATA SHEET

CROWN AREA STREET REHABILITATION PROJECT
Project No.: 44076

Source of Funds
Existing Budget:

Measure M2 Fund $25,000

Proposed Budget Transfers:

Measure M2 Fund from Project 44589 $680,000
Sewer Enterprise Fund from Project 51419 $45,000
TOTAL $750,000

Estimated Expenditures
Staff Design, Administration and Processing $32,208
Construction Contract $547,392
Estimated Surveying, Inspection, Testing,
and Contract Administration (15%) $82,109
Contingencies (15%) $82,109
TOTAL $743,818

Summary of Bids

Bid Opening: May 1, 2025
Engineer’s Estimate: $623,000

Contractor Base Bid Total

1. R.J. Noble Company $547,391.50

2. Onyx Paving Company, Inc. $555,000.00

3. Palp, Inc. DBA Excel Paving $612,373.00

4. Copp Contracting, Inc. $627,514.35

5. Sequel Contractors, Inc. $635,242.50

6. Hardy & Harper, Inc. $649,000.00

7. All American Asphalt $687,110.00