ATTACHMENT 2
BID SCHEDULE
UNION PACIFIC TRAIL - PHASE II
PROJECT NO. 54271
ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 MOBILIZATION 1 LS 94,000 94,000
STORMWATER POLLUTION PREVENTION PLAN 1 LS
2 (SWPPP) 25,000 25,000
3 TRAFFIC CONTROL 1 LS 20,200 20,200
4 CLEAR & GRUB 1 LS 65,000 65,000
5 DEMOLITION & REMOVALS 1 LS 30,000 30,000
6 EARTHWORK & GRADING 1 LS 145,000 145,000
7 RAILROAD BALLAST REMOVAL 250 CY 70 17,500
8 CONCRETE CURB 60 LF 62 3,720
9 CONCRETE CURB & GUTTER 125 LF 80 88JW 10,000
10 CONCRETE HEADER 7,784 LF 22 171,248
11 CURB RAMP WITH TRUNCATED DOMES 4 EA 5,200 20,800
12 TRUNCATED DOMES - CAST-IN-PLACE 2 EA 1,400 2,800
13 AC PAVEMENT - PEDESTRIAN THICKNESS 24,031 SF 5.50 132,170.50 CONCRETE HARDSCAPE - STANDARD - SF 14
14 1,909 26,726
PEDESTRIAN THICKNESS
15 CONCRETE HARDSCAPE - DECORATIVE - SF 22
1,167 25,674
PEDESTRIAN THICKNESS
DECOMPOSED GRANITE PAVING - SF
16 11,621 4.25 49,389.25
PEDESTRIAN THICKNESS
17 GRAUST MONNTORING WELL COVER TO 8 EA 900 7,200
FENCING - TUBULAR STEEL 851 LF 105 89,355
19 FENCING - WOOD SPLIT RAIL 707 LF 53 37,471
20 BOLLARD - REMOVABLE EA 2,500 15,000
21 DRAINAGE - AREA DRAIN 2 EA 750 1,500
22 DRAINAGE - HEADWALL 2 EA 4,600 9,200
23 DRAINAGE - 12" PVC PIPE & FITTINGS 60 LF 90 5400
TO BE SUBMITTED WITH BID
BD-14
BID SCHEDULE
UNION PACIFIC TRAIL - PHASE II
PROJECT NO. 54271
ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
24 DRAINAGE - RIPRAP 20 SF 150 3,000
25 SOLAr LIGHTING 28 EA 6,700 187,600
RECTANGULAR RAPID FLASHING BEACON
28 2 EA 7,000 14,000
SYSTEM
27 ROADWAY SIGNING & STRIPING 1 LS 10,000 10,000
TRAIL SIGNING & STRIPING 1 LS 8,200 8,200
29 WATER SERVICE - IRRIGATION 1 LS 1,000
1,000
30 IRRIGATION SYSTEM 1 LS 393,000 393,000
31 GROUNDCOVER - FLATS 13,776 EA 82,656
32 GROUNDCOVER - 1 GAL 610 EA 6,710
33 VINES - 1 GALLON 48 EA 17 816
34 SHRUBS - 1 GALLON 532 EA 13 6,916
35 SHRUBS - 5 GALLON 22 EA 26 572
35 SHRUBS - 15 GALLON 34 EA 94 3,196
-37 VINES -1 GALLON 48 EA
38 TREES - 15 GALLON 176 EA 160 28,160
39 MULCH 98,274 SF 0.30 29,482.20
40 TREE ROOT BARRIER 591 LF 10,638
41 SOIL AMENDMENTS 87,B17 SF 0.50 43,908.50
42 TURF REPAIR - INDEPENDENCE PARK 905 SF 3.50 3,167.50 43 LANDSCAPE MAINTENANCE PERIOD- 90 DAYS 1 LS 8,400 8,400 Base Bid Total $ 1,845,775.95
Unit prices are required for all bid items.
The Bidder shall total his/her bid. Unlt prices shall prevail in case amount disagrees with extension.
Prolect shall be awarded on the Base Bid. If applicable, the City may elect to use Bld Alterates after award.
Changes to elther Unit Price or Amount shall be striked-out and Inlalad.
TO BE SUBMITTED WITH BID
BD-15
BID SCHEDULE
UNION PACIFIC TRAIL - PHASE II
PROJECT NO. 54271
ESTIMATED
QUANTITY UNIT UNIT PRICE AMOUNT
Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on underto that such work, pulimon, lor, oil, and material a repre i a parto be endle teal ted no additional compensaton will be pald therefor.
may be constered on esponsie wit bid prices are lenicanty unbalanced to the pontal dotimant of the cly, the bld Company KASA Construction, Inc.
Name Diana Kasbar, President,
Signature sumalkale
Address 15148 Sierra Bonita Lane
City & Zip Code Chino, CA 91710
Phone Number (909) 457-8260
License Number 927544
TO BE SUBMITTED WITH BID
BD-18