Exhibit D
Rehabilitation and Maintenance Plan
Completed
1. Demo plywood siding at garage, waterproof and install stucco, prime and paint exterior of garage - Dec 2023
$7,200
2. Pa,sia roof replacement from rock roof at north side to 30-year comp shingles - May 2020.
3. Electrical panel upgrade - Feb 2020
$3,800
4. Fence and gate construction - Nov 2019
$7,050
5. Rear concrete for sidewalks and stairs - June 2018
$8,200
Scheduled
1. Repair exterior shingles of face of house, prime and paint - June 2025. $3,800
2. Roof replacement from rock roof at south, east and west sides - 2026. $16,000
3. Rehab existing wood windows on north side of house - 2027. $7,000
4. Ss, sab existing wood windows on east and west sides of house - 2028.
5. Rebuild rear wooden staircase - 2029.
$12,500
Replace fascia boards - 2030.
$8,500
7. Prepare, prime and paint exterior of house - 2031.
$15,000
8. Construct front planter beds - 2032.
$2,000