BID PROPOSAL

ADAMS-WEST AREA INFRASTRUCTURE IMPROVEMENTS
PROJECT NO. 53047

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS $20,000 $20,000
Water Pollution Control 1 LS $5,000 $5,000
3 Traffic Control 1 LS $10,000 $10,000
4 Remove Existing Sewer Manhole 4 EA $2,000 $8,000
5 Construct Precast Concrete Sewer Manhole 4 EA $5,000 $20,000 Replace Sewer Manhole Ring and Cover 3 EA $1,000 $3,000 Replace Sewer Lamphole Ring and Cover 1 EA $1,000 $1,000 8 Install 8" PVC Water Pipe 5,490 LF $130 $713,700
9 Install 6" PVC Water Pipe 110 LF $265 $29,150
10 Install 4" PVC Water Pipe 160 LF $150 $24,000
11 Install 8" Water Gate Valve Assembly 19 EA $3,000 $57,000 12 Install 4" Water Gate Valve Assembly 1 EA $2,000 $2,000 13 Install 8" PVC Under Crossing 1 EA $3,000 $3,000
14 Install 1" Water Service 135 EA $2,500 $337,500
Install Domestic Water Connection for 1" Water 10 LF $100 $1,000 15 Service
16 Remove Existing Water Meter Box 135 EA $50 $6,750
17 Install 2" Blow-Off Assembly EA $11,000 $11,000
18 Install Fire Hydrant Assembly (Standard Type) 13 EA $20,000 $260,000 19 Abandon Existing Water Valve and Valve Box 25 EA $500 $12,500 20 Remove Existing Fire Hydrant 10 EA $500 $5,000
21 Adjust Water Valve to Grade 35 EA $500 $17,500
22 4" AC Pavement 390 TON $150 $58,500
23 Street Lighting Conduit and Wiring Repair 100 LF $100 $10,000

TO BE SUBMOTED WITH BID

BID PROPOSAL

ADAMS-WEST AREA INFRASTRUCTURE IMPROVEMENTS
PROJECT NO. 53047

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
Base Bid Total $ $1,615,600.00
Unit prices are required for all bid items.

The Bidder shall total their bid. Unit prices shall prevail in case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award. additional compensation will be paid therefor.

If the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company Dominguez General Engineering, Inc.

Name Alejandro Dominguez
Signature
Address 11096 Pipeline Avenue
City & Zip Code Pomona, CA 91766
Phone Number (626)652-2622 or (909)461-3658
License Number 814046 - Class A