ATTACHMENT 1 – BUDGET DATA SHEET
EUCLID STREET SIDEWALK GAP CLOSURE
Project No.: 44072
Source of Funds
Existing Budget:
ARPA Revenue Replacement Fund $50,000
Proposed Budget Transfers:
Infrastructure Funds from Project 55057 $175,000
Drainage Capital Funds from Project 52591 $225,000
TOTAL $450,000
Estimated Expenditures
Staff Design, Administration and Processing $33,005
Tree Removals $6,963
Construction Contract $327,763
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $32,776
Contingencies (15%) $49,165
TOTAL $449,672
Summary of Bids
Bid Opening: June 4, 2025
Engineer’s Estimate: $432,700
Contractor
Base Bid Total
1. Towo Enterprise Inc
(1)$314,975.00
2. Zeco Inc
$327,762.50
3. Cali State Paving
$386,550.00
4. Premo Construction Inc
$388,290.00
5. Palp Inc, DBA Excel Paving
$389,485.00
6. Gentry General Engineering
$420,000.00
7. Golden Coast Construction
$429,999.99
8. CEM Construction Corp
$459,150.00
9. CT&T Concrete Paving Inc
$463,705.11
10. Matcon General Engineering
$465,481.95
11. Wright Construction Inc
$476,185.00
12. Leonida Builders Inc
$485,000.00
13. Lonerock, Inc
$545,050.00
14. HZS Engineering
$617,700.00
The bid from Towo Enterprise was found to be non-responsive by City staff and City Attorney.