081925 PW Courtney-Ash Area Water Main Replacement Budget Data Sheet

City Council - Successor Agency - Housing Authority
August 19, 2025

Document
081925 PW Courtney-Ash Area Water Main Replacement Budget Data Sheet
Meeting
August 19, 2025
Body
City Council - Successor Agency - Housing Authority
Original file
48 KB
Text extracted from the city's file for reading and search. Open the original on fullerton.legistar1.com. That file is the official record.

ATTACHMENT 1 – BUDGET DATA SHEET

COURTNEY-ASH AREA WATER MAIN REPLACEMENT PROJECT
Project No.: 53049

Source of Funds
Existing Budget:

Water Fund $150,000

Proposed Budget Transfers:

Water Fund from Project 53250 $1,830,000
TOTAL $1,980,000

Estimated Expenditures
Project Design $124,250
Construction Contract $1,579,250
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $118,500
Contingencies (10%) $158,000
TOTAL $1,980,000

Summary of Bids

Bid Opening: July 14, 2025
Engineer’s Estimate: $2,453,928

Contractor
Location Base Bid Total

1. Williams Pipeline Contractors, Inc Mission Hills, CA $1,579,250

2. Big Ben, Inc. Irvine, CA $1,941,160

3. Stephen Doreck Equipment Rentals Pico Rivera, CA $2,023,500

4. Dominguez General Engineering, Inc Pomona, CA $2,210,450

5. CEM Construction Corp. Montebello, CA $2,227,950

6. All Cities Engineering Inc. Ontario, CA $2,316,100

7. American Pipeline Services Monrovia, CA $2,599,400

8. LoneRock Inc. Irvine, CA $3,488,800