ATTACHMENT 1 – BUDGET DATA SHEET
SKYLINE-RAYMOND AREA WATER MAIN REPLACEMENT
Project No.: 53050
Source of Funds
Existing Budget:
Water Fund $515,000
Proposed Budget Transfers:
Water Fund from Project 53250 $3,045,000
TOTAL $3,560,000
Estimated Expenditures
Project Design - Consultants $421,405
Staff Design, Administration and Processing $27,676
Construction Contract $2,647,078
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $198,531
Contingencies (10%) $264,708
TOTAL $3,559,398
Summary of Bids
Bid Opening: September 17th, 2025
Consultant Engineer’s Estimate: $3,650,000
Contractor
Base Bid Total
1. All Cities Engineering, Inc.
$ 2,647,078.00
2. Big Ben, Inc.
$ 2,988,100.00
3. Dominguez General Engineering Inc.
$ 3,113,200.00
4. Stephen Doreck Equipment Rentals, Inc.
$ 3,240,345.00
5. Williams Pipeline Contractors, Inc.
$ 3,436,550.00
6. JA Salazar Construction and Supply Corp.
$ 3,886,800.00
7. CEM Construction Corporation
$ 3,968,750.00
8. Toro Enterprises, Inc.
$ 4,196,116.00
9. MNR Construction, Inc,
$ 4,511,700.00
(1) = Submitted bid amount was $4,511,650, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $4,511,700.