Kelsey-Holmes Residence 400 W Brookdale Place, Fullerton, CA Proposed Mills Act Projects
Project Timing Cost Duration
Install Moisture Barrier - East SideSpring 2026 $3,5001 month Roof Repair Summer 2026 $5,0002 weeks
Window Repair (various) Ongoing $8,0002 years
Retaining Wall replacment Fall 2026 $30,0006 months
Stucco Repair (various) Spring 2026 $5,0002 months
Paint House Summer 2027 $35,0003 months
Side drainage improvements Spring 2026 $2,0001 month
Termite/Dry rot repair Spring 2026 $1,0001 week
Front Walkway/Patio improvmentsSpring 2028 $10,0002 months
111825 CED Mills Act 400 W Brookdale Rehabilitation/Maintenance Plan
City Council - Successor Agency - Housing Authority
November 18, 2025
- Document
- 111825 CED Mills Act 400 W Brookdale Rehabilitation/Maintenance Plan
- Meeting
- November 18, 2025
- Body
- City Council - Successor Agency - Housing Authority
- Original file
- 18 KB
Text extracted from the city's file for reading and search. Open the original on fullerton.legistar1.com. That file is the official record.