BID SCHEDULE
SUNCLIPSE WELL 10
TEMPORARY PFAS TREATMENT PLANT
PROJECT NO. 53023
ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
Mobilization, Demobilization & Cleanup, Including 1 LS $94,207°° 1 Storm Water Compliance $94,207"
Furnish and Install Above Grade Piping and 1 IS #310, 372° $361,3278 2 Appurtenances
Furnish and Install Site Electrical and Utility Power 1 LS $60,606° $60, 606l 4 Prior and Complete al Start up, Testing, and 1 LS $30,087 $30,087°° 5 Prepare O&M Manuals and Record Drawings 1 L$ $1,000 " $1,000 % Provide Worker Protection and Safety, Sheeting,
1 LS $500°. $500 l
Shoring, and Bracing
7 Provide the Builder's All Risk Insurance 1 LS $76005°° $7,605° SCHEDULE A: Steel Plate Foundation
Install and Coordinate the Temporary IX Treatment
8 System and Appurtenances for Steel Plate 1 LS $71,965 $71,9l5 Foundation
Furnish, Install, and Coordinate Site Modifications 1 $308,0079 9 LS 8308,007"9
for Steel Plate Foundation
Base Bid Total $935,304°°
BID ALTERNATIVE: SCHEDULE B: Concrete Slab Foundation
Install and Coordinate the Temporary IX Treatment
10 System and Appurtenances for Concrete Slab 1 LS 480,000°° $80,000° Foundation
Furnish, Install, and Coordinate Site Modifications $340,000340,000° 11 1 LS
for Concrete Slab Foundation
Alternative Bid Total $ 420,000 *
- Unit prices are required for all bid items.
- The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension. - Project shall be awarded on the Base Bid. Schedule A is included in the Base Bid. If applicable, the City may elect to use Bid Alternates after award. The City reserves the right to replace bid items 8 thru 9 with bid items 10 thru 11. - Changes to either Unit Price or Amount shall be striked-out and initialed. - Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.
- If the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.
Company SCW Contracting Corporation
Name Andrew Scrape - President
Signature
License Number 630435
TO BE SUBMITTED WITH BID
BD-14