ATTACHMENT 1 – BUDGET DATA SHEET
YUCCA AREA WATER MAIN REPLACEMENT PROJECT
Project No.: 53057
Source of Funds
Existing Budget:
Water Fund $150,000
Proposed Budget Transfers:
Water Fund from Project 53250 $1,869,000
TOTAL $2,019,000
Estimated Expenditures
Project Design $120,657
Construction Contract $1,615,495
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $121,298
Contingencies (10%) $161,550
TOTAL $2,008,000
Summary of Bids
Bid Opening: January 28, 2026
Engineer’s Estimate: $2,311,400
Contractor Location Base Bid Total
1. Dominguez General Engineering, Inc Pomona, CA $1,615,495.00
2. Williams Pipeline Contractors, Inc Mission Hills, CA $1,682,475.00
3. All Cities Engineering Inc. Ontario, CA $1,750,515.00
4. Big Ben, Inc. Irvine, CA $1,829,275.00
5. Stephen Doreck Equipment Rentals Pico Rivera, CA $2,001,000.00
6. J.A. Salazar Construction and Supply Corp. La Habra, CA $2,215,105.00
7. Armstrong Cal Builders Inc Stanton, CA $2,286,495.00
8. GHC Pipeline LLC Riverside, CA $2,531,519.30
9. Pyramid Building & Engineering, Inc. Hesperia, CA $2,575,042.11