Agenda Report
Fullerton City Council
MEETING DATE: February 17, 2026
TO: CITY COUNCIL / SUCCESSOR AGENCY
SUBMITTED BY: stephen bise, p.e., public works director PREPARED BY: DAVID GRANTHAM, P.E., CITY ENGINEER
JUAN ZAVALA, P.E., PRINCIPAL CIVIL ENGINEER

MARIANA ROCHA, ASSISTANT PLAN CHECK ENGINEER
SUBJECT: $239,992.38 contract with Golden Coast CONSTRUCTION FOR CURB and GUTTER / SIDEWALK PROJECT Fiscal Year 2024-26

SUMMARY
Award $239,992.38 construction contract to Golden Coast Construction for the Curb and Gutter / Sidewalk Project Fiscal Year (FY) 2024-26.

PROPOSED MOTION
Approve Curb and Gutter / Sidewalk Project FY 2024-26 plans and specifications.

Award $239,992.38 construction contract for Curb and Gutter / Sidewalk Project FY 2024-26 to Golden Coast Construction and authorize City Manager, or designee, to execute and administer the contract, in a form approved by the City Attorney.

Authorize Public Works Director, or designee, to approve change orders for construction and professional engineering construction support services within the approved project budget.

ALTERNATIVE OPTIONS
Approve the Proposed Motion
Reject all bids
Other options brought by City Council

STAFF RECOMMENDATION
Staff recommends the Proposed Motion.

CITY MANAGER REMARKS
None.

PRIORITY POLICY STATEMENT
This item matches the following Priority Policy Statements:

Public Safety
Infrastructure and City Assets.

FISCAL IMPACT
The Fiscal Year 2025-26 Adopted Capital Improvement Program (CIP) Budget has sufficient funding for Project 44797 Curb and Gutter / Sidewalk Project FY 2024-26 provided from Measure M2 funds within the Capital Projects Fund (Fund 74).

Staff attached a budget Data Sheet / Summary of Bids and the Contractor Bid Schedule for reference (Attachments 1 and 2).

BACKGROUND AND DISCUSSION
Staff programs curb and gutter and sidewalk projects annually to repair damaged curb, gutter and sidewalk at locations throughout the City, identifying project locations through a combination of resident requests, information provided by the Public Works – Maintenance Division and staff field observations. Staff evaluates and prioritizes Identified locations based on severity of damage, public safety considerations and potential liability exposure. Staff coordinates repair work with other street rehabilitation capital improvement projects and planned private utility work to minimize conflicts and improve construction efficiency. The project for this year covers eighty locations.

The City received nineteen bids on January 29, 2026. Golden Coast Construction of La Habra submitted the lowest responsible base bid totaling $239,992.38. Staff reviewed the bid and found it acceptable.

Construction would tentatively start March 2026 with anticipated project completion in June 2026. The contractor would notify impacted residents and upcoming construction activities and potential impacts.

Staff prepared an environmental assessment in accordance with California Environmental Quality Act Guidelines and determined that the project is categorically exempt.

Attachments:

Attachment 1 – Budget Data / Summary of Bids
Attachment 2 – Bid Schedule
Attachment 3 – Draft Agreement
cc: Interim City Manager Eddie Manfro
Contract for Curb and Gutter / Sidewalk Project Fiscal Year 2024-26 February 17, 2026 - Page 2

← All documents from this meeting