ATTACHMENT 1 – BUDGET DATA SHEET
E. SANTA FE PARKING LOT REHABILITATION PROJECT
Project No.: 55067
Source of Funds
Existing Budget:
Downtown Parking Program/General Fund $50,000
Proposed Budget Transfers:
Downtown Parking Program/General Fund from Project 55450 $350,000 Infrastructure Funds from Project 55450 $65,000
TOTAL $465,000
Estimated Expenditures
Project Design - Consultants $23,300
Staff Design, Administration and Processing $3,000
Construction Contract $345,000
Landscape and Tree Removals and Updates $12,500
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $34,500
Contingencies (12.5%) $43,125
TOTAL $461,425
Summary of Bids
Bid Opening: February 12, 2026
Engineer’s Estimate: $420,000
Contractor
Base Bid Total
1. Onyx Paving Company, Inc.
$345,000.00
2. PaveWest, LLC
$368,988.00
3. Towo Enterprise Inc
$374,075.00
4. All American Asphalt
$379,496.00
5. Oppenheimer National
$396,994.00
6. LC Paving and Sealing
$402,873.75
7. A2ZConstruct Inc
$414,550.00
8. TVR Construction Engineering LLC
$422,805.50
9. Asphalt, Fabric and Engineering
$442,538.00
10. FS Contractors, Inc.
$452,420.00
11. Horizons Construction Company Int'l Inc.
$476,640.00
12. Roadway Engineering and Construction Corp.
$477,043.00
13. Paveco Construction, Inc.
$484,705.82
14. Prestige Prime Engineering
$540,572.50
15. PALP Inc. dba Excel Paving Company
$622,532.00
16. L.M.T Enterprises, Inc.
$635,891.60
17. ORTIZ and SON, INC
$714,999.00
18. Shiraz Construction
$744,444.00