ATTACHMENT 2 – BID SCHEDULE
E. SANTA FE PARKING LOT REHABILITATION PROJECT
Project No.: 55067
oNYx paving company
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
1 MOBILIZATION
1 LS
$22,000.00
$22,000.00
2 WATER POLLUTION CONTROL
1 LS
$3,000.00
$3,000.00
3 TRAFFIC CONTROL
1 LS
$22,000.00
$22,000.00
4 DEMOLITION & REMOVALS
1 LS
$22,000.00
$22,000.00
5 PAVEMENT DIGOUTS/REPAIRS
2,300
SF
$5.00
$11,500.00
6 COLD MILL - 3" THICKNESS
46,000
SF
$0.60
$27,600.00
7 COLD MILL - 6" THICKNESS
1,150
SF
$5.00
$5,750.00
8 AC PAVEMENT
880
TON
$111.00
$97,680.00
9 PCC PAVEMENT
1,215
SF
$18.00
$21,870.00
10 CURB - 6"
830
LF
$30.00
$24,900.00
11 CURB & GUTTER - 6"
65 LF
$88.00
$5,720.00
12 CROSS GUTTER & SPANDREL
410
SF
$30.00
$12,300.00
13 CURB RAMP TYPE A INCUDING DECORATIVE FINISH
2 EA
$4,000.00
$8,000.00
14 CURB RAMP TYPE F INCUDING DECORATIVE FINISH
3 EA
$3,000.00
$9,000.00
15 DECORATIVE SIDEWALK WITH PAVERS
530
SF
$22.00
$11,660.00
16 ADJUST SEWER MANHOLE TO GRADE
5 EA
$1,250.00
$6,250.00
17 ADJUST SEWER CLEANOUT TO GRADE
4 EA
$1,250.00
$5,000.00
18 ADJUST WATER VALVE TO GRADE
1 EA
$750.00
$750.00
19 CONCRETE WHEEL STOP
12 EA
$105.00
$1,260.00
20 TRAFFIC SIGNING AND STRIPING
1 LS
$18,510.00
$18,510.00
21 STREET LIGHT CONDUIT AND WIRING REPAIR
50 LF
$165.00
$8,250.00
TOTAL
$345,000.00
030326 PW Santa Fe Parking Lot Rehabilitation Bid Schedule
City Council - Successor Agency - Housing Authority
March 3, 2026
- Document
- 030326 PW Santa Fe Parking Lot Rehabilitation Bid Schedule
- Meeting
- March 3, 2026
- Body
- City Council - Successor Agency - Housing Authority
- Original file
- 23 KB
Text extracted from the city's file for reading and search. Open the original on fullerton.legistar1.com. That file is the official record.