ATTACHMENT 1 – BUDGET DATA SHEET
WATER VALVE REPLACEMENT PROJECT
Project No.: 53016
Source of Funds
Existing Budget:
Water Fund $0
Proposed Budget Transfers:
Water Fund from Project 53002 $446,000
TOTAL $446,000
Estimated Expenditures
Design Administration $1,000
Construction Contract $393,800
Estimated Inspection, Testing,
and Contract Administration (8%) $31,504
Contingencies (5%) $19,690
TOTAL $445,994
Summary of Bids
Bid Opening: February 9, 2026
Engineer’s Estimate: $444,500
Contractor
Location
Base Bid Total
1. Premo Construction, Inc.
Tustin, CA
$393,800
2. Gentry General Engineering, Inc.
Colton, CA
$402,186
3. Dominguez General Engineering, Inc
Pomona, CA
$409,000
4. Williams Pipeline Contractors, Inc.
Mission Hills, CA
$421,000
5. All Cities Engineering Inc.
Riverside, CA
$430,050
6. Big Ben, Inc.
Irvine, CA
$476,000
7. Stephen Doreck Equipment Rentals, Inc
Pico Rivera, CA
$521,450
8. J.A Salazar Construction
La Habra, CA
$521,500
9. We R Builders, Inc.
Riverside, CA
$531,900
10. Cedro Construction Inc.
Santa Paula, CA
$589,902
11. RE Chaffee Construction Inc.
Wrightwood, CA
$674,000
(1) = Submitted bid amount was $597,909, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $589,902.