BID SCHEDULE
WATER VALVE REPLACEMENT PROJECT
PROJECT NO. 53016
NO. TTEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Detail 1 Magnolia and Franklin 1 LS
$25,059
2 Detail 2 Pioneer W/O Gilbert 1 LS
$25,059
3 Detail 3 Roosevelt and Commonwealth 1 LS
$14,214
4 Detail 4 Euclid and Ash LS $36,904
5 Detail 5 Orangethorpe E/O Euclid 1 LS 18.714
6 Detail 6 Orangethorpe and Highland 1 LS $29,727
7 Detail 7 Knepp W/O Harbor 1 LS $21,332
8 Detail 8 Commonwealth and Lawrence 1 LS $22,690
Detail 9 Brea S/O Juniper 1 LS $18,952
10 Detail 10 Nutwood and State College 1 LS $16,583
Detail 11 College and Commonwealth 1 LS
$16,583
12 Detail 12 Placentia N/O Nutwood 1 LS $18,950
13 Option No. 1 - Similar to location on Detail 2 3 LS $20,321 $60,963 14 Option No. 2 - Similar to location on Detail 8 3 LS $22,690 $68,070 Base Bid Total $ $393,800
Unit prices are required for all bid items.
The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension.
Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award.
Changes to either Unit Price or Amount shall be striked-out and initialed.
Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.
If the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.
Company premo construction Ina
Name Mohammad Ghiassi
Signature y
License Number 867514
TO BE SUBMITTED WITH BID
BD-14