ATTACHMENT 2 – BID SCHEDULE
BAKER AVENUE REHABILITATION PROJECT
Project No.: 44088
R.J. NOBLE COMPANY
Line
Item
Description Quantity Unit of
Measure
Unit Cost Total
1 MOBILIZATION 1 LS $40,000.00 $40,000.00
2 WATER POLLUTION CONTROL 1 LS $7,000.00 $7,000.00
3 TRAFFIC CONTROL 1 LS $15,000.00 $15,000.00
4 REMOVE EXISTING AND REPLACE 6" PCC
CURB & GUTTER
360 LF $118.00 $42,480.00
5 REMOVE EXISTING AND REPLACE
SIDEWALK
2,150 SF $12.00 $25,800.00
6 REMOVE EXISTING AND REPLACE ADA
CURB RAMP
8 EA $5,800.00 $46,400.00
7 REMOVE EXISTING AND REPLACE
MODIFIED ALLEY APPROACH DRIVEWAY
1,675 SF $29.00 $48,575.00
8 RECONSTRUCT PARKWAY CULVERT LID 1 EA $5,500.00 $5,500.00 9 REMOVE EXISTING AND RECONSTRUCT
CONCRETE HARDSCAPE ON PRIVATE
PROPERTY
200 SF $13.00 $2,600.00
10 COLDMILL - 4" 65,750 SF $0.55 $36,162.50
11 PAVEMENT DIG OUTS/REPAIRS (AS NEEDED
- SEE SPECIAL PROVISIONS)
6,575 SF $3.75 $24,656.25
12 AC PAVEMENT 1,650 TON $112.00 $184,800.00
13 ADJUST WATER VALVE TO GRADE 16 EA $1,100.00 $17,600.00 14 ADJUST MH TO GRADE WITH NEW FRAME
& COVER
6 EA $1,900.00 $11,400.00
15 SIGNING & STRIPING 1 LS $12,000.00 $12,000.00
16 TRAFFIC LIGHT CONDUIT AND WIRING
REPAIR
100 LF $135.00 $13,500.00
TOTAL $533,473.75