ROAD MAINTANANCE AND REHABILITATION ACCOUNT (RMRA)/ SENATE BILL 1 (SB1) RESOLUTION APRIL 21, 2026
SB1 FUNDS ALLOCATION
Background
Senate Bill 1 (SB1), known as the Road Repair and Accountability Act (RMRA) of 2017.
Intent is to address/fund basic roadway maintenance, rehabilitation and critical safety needs.
RMRA revenues are the result of increases in the fuel excise taxes, diesel fuel sales taxes and vehicle registration fees.
We have programmed and completed projects since 2018 using SB1 funds.
Expected SB1 funding for FY 2026-27 is approximately $4 million.
Previous SB1 Projects
3 FY 2017-18
Project 1 - Chapman Avenue (Acacia Ave to SR-57)
FY 2018-19
Project 2 - Commonwealth Avenue (Balcom Ave to Montegue Ave) Raymond Avenue (Commonwealth Ave to Chapman Ave)
FY 2019-20
Project 3 - Euclid Street (Williamson Ave to Fern Dr)
FY 2020-21
Project 4A - Euclid Street (Fern Dr to Bastanchury Rd) & Valley View Pl Project 4B - Orangethorpe Avenue (Woods Ave to Highland Ave) FY 2021-22
Project 5A – Rosecrans Avenue (City Limits to Sunny Ridge) Project 5B - Valencia Avenue (Magnolia Ave to Gilbert St) FY 2022-23
Project 6A – Associated Road (Rolling Hills to Imperial Hwy) Project 6B - Orangethorpe Avenue (State College to Placentia Ave) FY 2023-24
Project 7A – State College Blvd (Yorba Linda Blvd to City Limits) Project 7B – Slurry Seal (Various Residential Streets)
FY 2024-25
Project 8 – Maplewood Area
FY 2025-26
Project 9A – Sunny Hills- Twilight Area
Project 9B – Candlewood Area
Funding Requirements
To receive funds, the California Transportation Commission (CTC) requires City submit a list of proposed projects utilizing SB1 revenue by July 1, 2026.
CTC submittal requirements include:
Public review of proposed projects.
Infrastructure and Natural Resources Advisory Committee (INRAC) reviewed and supported the projects at their March 16, 2026 meeting.
Use of Pavement Management Plan (PMP) to develop the list of potential projects.
City Council approval of Resolution identifying the list of projects.
Potential Arterial Street Projects
5 Project 1 – Rosecrans Avenue
Camino Centraloma to Camino Loma
Project 2 – Rosecrans Avenue
Sunny Ridge Dr to Gilbert St
Project 3 – Euclid St
SR-91 Interchange to Valencia Dr
Project 4 – Valencia Drive
Euclid St to Richman Ave
Project 5 – Malvern Ave
Bastanchury Rd to Basque Ave
Project 6 – Commonwealth Avenue
Montague Ave to State College Blvd
Project 7 – Commonwealth Avenue
State College Blvd to Chapman Ave
Project 8 – Yorba Linda Boulevard
State College Blvd to Bradford Ave
Project 9 – Bastanchury Road
Puente St to Brea Blvd
Projects 3 & 8 are not recommended at this time, since both received grant funding for design only, and construction will not be ready in the upcoming fiscal year. Better suited for future SB1 allocations or other grant opportunities once design is complete.
Projects 6 & 7 are not recommended at this time as they are programmed for future water main replacement
Potential Local Street Projects
6 Project 1 – Lindendale Area
Project 2 – Courtney - Ash Area
Project 3 – Rancho-Verona-Yucca Area
Project 4 – Coronado Area
Project 5 – Gregory Area
Project 6 – Cannon-Sheppard Area
Project 7 – Acacia Avenue
Commonwealth Ave to Victoria Dr
Project 8 – Parks Road
Bastanchury Rd to Rosecrans Ave
Project 5-6 includes streets in poor and good condition Project 7-8 are adjacent to a school site
Staff Recommended SB1 Project #1
7 RANCHO-VERONA-YUCCA AREA
Residential Neighborhood (~2.8 miles)
Estimated Total Project Cost = $3.7M
Pavement Rehabilitation
4” Grind & Overlay (expected)
Concrete curb & gutter repair, cross-gutter and spandrels, minor sidewalk repair, curb ramps, & driveway repairs.
Background:
Water Main Replacements
Phase 1: Construction completed in Fall 2024 (Magenta)
Phase 2: Anticipated to be complete by end of this calendar year 2026 (Blue)
Staff Recommended SB1 Project #2
8 STATE COLLEGE BLVD
Yorba Linda Blvd to City Limits
Supplemental Funding Allocation
Estimated Total Project Cost = $3.6M
Pavement Rehabilitation
2” Grind & Overlay
Concrete curb ramps, curb & gutter repair, sidewalk repair, driveway repair.
Previously SB1 project for FY 2023-24.
Recommendation
Adopt the proposed Resolution listing Rancho-Verona-Yucca Area and State College Boulevard for pavement rehabilitation for Fiscal Year 2026-27 funded by SB1, the Road Repair and Accountability Act of 2017.
Questions?