ATTACHMENT 1 – BUDGET DATA SHEET
LAGUNA AND LAS PALMAS PUMP STATIONS EMERGENCY GENERATOR SETS PROJECT Project No.: 53024
Source of Funds
Existing Budget:
Water Fund $3,081,198
Estimated Expenditures
Project Design - Consultants $183,740
Staff Design, Administration and Processing $20,500
Generator Purchase $338,139
Construction Contract $636,480
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $63,648
Contingencies (20%) $127,296
TOTAL $1,369,803
Summary of Bids
Bid Opening: June 9, 2026
Engineer’s Estimate: $1,269,740
Contractor
Base Bid Total
1. Cora Constructors Inc
$636,480.00
2. Metro Builders & Engineers Group, Ltd.
$910,657.00
3. Vicon Enterprise Inc
$914,050.00
4. MC Electric
$1,061,000.00
5. U.S. Builders & Consultants Inc.
$1,078,400.00
6. Premo Construction Inc
$1,104,800.00
7. Mel Smith Electric, Inc.
$1,164,400.00
8. Marjani Builders, Inc
$1,167,499.00
9. Minako America Corporation
$2,404,000.00