ATTACHMENT 2 – BID SCHEDULE

HARBOR BOULEVARD REHABILITATION PROJECT
Project No.: 44083
R.J. NOBLE COMPANY

BASE BID
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
1 MOBILIZATION
1 LS
$55,000.00
$55,000.00
2 WATER POLLUTION CONTROL
1 LS
$10,000.00
$10,000.00
3 TRAFFIC CONTROL
1 LS
$17,000.00
$17,000.00
4 REMOVE AND CONSTRUCT ALLEY DRIVEWAY APPROACH
1000
SF
$44.00
$44,000.00
5 REMOVE AND CONSTRUCT 4" SIDEWALK
3350
SF
$15.50
$51,925.00
6 REMOVE AND RECONSTRUCT 8" CURB & GUTTER
10 LF
$200.00
$2,000.00
7 REMOVE AND RECONSTRUCT CURB ACCESS RAMP
2 EA
$12,900.00
$25,800.00
8 COLDMILL - 2"
97000
SF
$0.19
$18,430.00
9 COLDMILL - 3"
161000
SF
$0.19
$30,590.00
10 PAVEMENT DIGOUTS/REPAIRS (AS NEEDED)
12500
SF
$5.20
$65,000.00
11 ASPHALT RUBBERIZED HOT MIX (ARHM)
4,300
TON
$135.00
$580,500.00
12 ADJUST WATER VALVE TO GRADE
38 EA
$1,300.00
$49,400.00
13 ADJUST MANHOLE TO GRADE
4 EA
$1,100.00
$4,400.00
14 ADJUST ORANGE COUNTY SANITATION DISTRICT MANHOLE TO GRADE 5 EA
$5,500.00
$27,500.00
15 REPLACE SEWER MANHOLE FRAME & COVER. ADJUST TO GRADE 5 EA
$2,500.00
$12,500.00
16 SIGNING AND STRIPING
1 LS
$60,000.00
$60,000.00
17 TRAFFIC DETECTOR LOOP
52 EA
$450.00
$23,400.00
18 TRAFFIC SIGNAL CONDUIT
210
LF
$103.00
$21,630.00
19 STREET LIGHT CONDUIT AND WIRING REPAIR (AS NEEDED)
100
LF
$150.00
$15,000.00
TOTAL
$1,114,075

BID ALTERNATE
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
A1

REMOVE AND RECONSTRUCT CURB ACCESS RAMP
1 EA
$24,000.00
$24,000.00