ATTACHMENT 1 – BUDGET DATA SHEET
VALLEY VIEW-WOODS AREA WATER MAIN REPLACEMENT PROJECT
Project No.: 53059
Source of Funds
Existing Budget:
Water Fund $300,000
Proposed Budget Transfers:
Water Fund from Project 53250 $2,388,000
TOTAL $2,688,000
Estimated Expenditures
Project Design $161,272
Construction Contract $2,150,130
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $161,260
Contingencies (10%) $215,013
TOTAL $2,687,675
Summary of Bids
Bid Opening: July 13, 2026
Engineer’s Estimate: $2,475,000
Contractor
Location
Base Bid Total
1. All Cities Engineering Inc.
Riverside, CA
$2,150,130.00
2. Q&E Pipeline Company
Pomona, CA
$2,183,735.00
3. Dominguez General Engineering, Inc
Pomona, CA
$2,306,950.00
4. Williams Pipeline Contractors, Inc
Mission Hills, CA
$2,333,880.00
5. American Pipeline Services
Monrovia, CA
$2,366,300.00
6. Big Ben, Inc.
Irvine, CA
$2,399,230.00
7. Ortiz Construction Services
Buena Park, CA
$2,438,317.42
8. Elegant Construction Inc
Irvine, CA
$2,455,250.00
9. U.S. Builders & Consultants Inc.
Irvine, CA
$2,548,400.00
10. Valverde Construction, Inc.
Santa Fe Springs, CA
$2,554,178.00
11. CEM Construction
Montebello, CA
$2,835,600.00
12. J.A. Salazar Construction and Supply Corp.
La Habra, CA
$2,897,460.00
13. KASA Construction, Inc
Chino, CA
$2,919,580.00
14. T.E. Roberts Inc.
Irvine, CA
$3,288,224.00
15. ARB, Inc.
Irvine, CA
$3,323,750.00