ATTACHMENT 2 – BID SCHEDULE
STORM DRAIN REPAIR – SUNNY CREST ALLEY
Project No.: 52025
DIAMOND CONSTRUCTION AND DESIGN
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
1 MOBILIZATION
1 LS
$11,250.00
$11,250.00
2 WATER POLUTION CONTROL
1 LS
$5,900.00
$5,900.00
3 TRAFFIC CONTROL
1 LS
$22,000.00
$22,000.00
4 15" RCP STORM DRAIN 1500D
375
LF
$180.00
$67,500.00
5 12" RCP STORM DRAIN 1500D
40 LF
$180.00
$7,200.00
6 STANDARD CATCH BASIN AND LOCAL DEPRESSION
2 EA
$5,600.00
$11,200.00
7 REINFORCED CONCRETE COLLAR
1 EA
$1,250.00
$1,250.00
8 CONNECT TO EXISTING CATCH BASIN
1 EA
$3,750.00
$3,750.00
9 REMOVE EXISTING CATCH BASIN
2 EA
$4,200.00
$8,400.00
10 REPLACE CATCH BASIN LID
1 EA
$2,000.00
$2,000.00
11 ABANDON EXISTING STORM DRAIN IN PLACE
1 LS
$950.00
$950.00
12 REMOVE EXISTING STORM DRAIN
1 LS
$22,000.00
$22,000.00
13 REMOVE AND CONSTRUCT 4" SIDEWALK
50 SF
$24.00
$1,200.00
14 REMOVE AND RECONSTRUCT CROSS GUTTER
240
SF
$80.00
$19,200.00
15 REMOVE AND RECONSTRUCT DRIVEWAY APPROACH
110
SF
$56.00
$6,160.00
16 REMOVE AND RECONSTRUCT ALLEY ACCESS RAMP
1 EA
$7,800.00
$7,800.00
17 2" COLDMILL
1750
SF
$5.00
$8,750.00
18 AC PAVEMENT
25 TON
$525.00
$13,125.00
19 ADJUST EXISTING MANHOLE TO GRADE
1 EA
$1,750.00
$1,750.00
20 REMOVE AND INSTALL 42" HIGH BOLLARDS
4 EA
$1,500.00
$6,000.00
21 VINYL TRAIL FENCING
100
LF
$325.00
$32,500.00
22 CHAIN LINK FENCING
20 LF
$275.00
$5,500.00
23 LANDSCAPING AND IRRIGATION
1 LS
$19,900.00
$19,900.00
TOTAL
$285,285.00