100626 PW Airport Southeast Hangars Roof Rehabilitation Project Budget Data

City Council - Successor Agency - Housing Authority
October 6, 2026

Document
100626 PW Airport Southeast Hangars Roof Rehabilitation Project Budget Data
Meeting
October 6, 2026
Body
City Council - Successor Agency - Housing Authority
Original file
22 KB
Text extracted from the city's file for reading and search. Open the original on fullerton.legistar1.com. That file is the official record.

ATTACHMENT 1 – BUDGET DATA SHEET

AIRPORT SOUTHEAST HANGARS ROOF REHABILITATION PROJECT
Project No.: 49018
Source of Funds
Existing Budget:

FAA BIL AIP Grant $1,173,000
TOTAL $1,173,000
Estimated Expenditures
Project Design - Consultants $37,221
Staff Design, Administration and Processing $40,000
Construction Contract $661,746
Estimated Inspection, Testing,
and Contract Administration (10%) $66,175
Contingencies (10%) $66,175
TOTAL $871,317
Summary of Bids
Bid Opening: September 22, 2026
Engineer’s Estimate: $650,000
Contractor
Base Bid Total
Bid Alt Total

1. Commercial & Industrial Roofing Co., Inc.
$647,425
$57,500

2. Best Contracting Services, Inc.
$876,256
$207,000

3. California Sheet Metal Works, Inc
$2,567,472
$147,315

4. AME Builders Inc dba AME Roofing
$2,990,129
$149,603

5. Southland Roofing, Inc.
$3,550,866
$138,000