ATTACHMENT 2 – BID SCHEDULE
STATE COLLEGE BLOULEVARD STREET REHABILITATION PROJECT
Project No.: 44068
ALL AMERICAN ASPHALT
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
1 MOBILIZATION
1 LS
$65,000.00
$65,000.00
2 TRAFFIC CONTROL
1 LS
$163,877.00
$163,877.00
3 WATER POLLUTION CONTROL
1 LS
$3,000.00
$3,000.00
4 TRAFFIC STRIPING AND MARKINGS
1 LS
$135,000.00
$135,000.00
5 CURB AND GUTTER
120
LF
$115.00
$13,800.00
6 SIDEWALK
9000
SF
$10.50
$94,500.00
7 ACCESS RAMP
27 EA
$5,400.00
$145,800.00
8 MEDIAN RAMPS
3 EA
$1,800.00
$5,400.00
9 CROSS GUTTER / SPANDREL / DRIVEWAY
6000
SF
$30.00
$180,000.00
10 2" COLD MILL
596100
SF
$0.35
$208,635.00
11 AC DIGOUTS
15000
SF
$11.00
$165,000.00
12 ASPHALT RUBBER HOT MIX
7500
TON
$128.00
$960,000.00
13 ADJUST SEWER MANHOLE COVER TO GRADE
17 EA
$1,400.00
$23,800.00
14 ADJUST WATER VALVE COVER TO GRADE
48 EA
$1,200.00
$57,600.00
15 ADJUST WATER MANHOLE TO GRADE
3 EA
$1,400.00
$4,200.00
16 ADJUST STORM DRAIN MANHOLE COVER TO GRADE
3 EA
$1,400.00
$4,200.00
17 ADJUST OC SAN MANHOLE COVER TO GRADE
2 EA
$3,500.00
$7,000.00
18 REMOVE AND RECONSTRUCT CATCH BASIN LID
2 EA
$9,750.00
$19,500.00
19 SEWER POINT REPAIR
5 EA
$19,460.00
$97,300.00
20 STEET LIGHT CONDUIT
100
LF
$150.00
$15,000.00
21 STAMPED CONCRETE
700
SF
$15.00
$10,500.00
TOTAL