ATTACHMENT 2 – BID SCHEDULE
MISCELLANOUS STORM DRAIN LINING FY 2026-27
Project No.: 52027
VORTEX SERVICES, LLC
Line Item
Description
Quantity
Unit of Measure
Unit Cost
Total
1 MOBILIZATION
1 LS
$8,500.00
$8,500.00
2 WATER POLLUTION CONTROL
1 LS
$2,500.00
$2,500.00
3 TRAFFIC CONTROL
1 LS
$2,500.00
$2,500.00
4 CCTV PRELIMINARY AND POST PIPE INSPECTION AND CLEANING 1 LS
$17,450.00
$17,450.00
5 REMOVE AND REPLACE DRAIN INLET
1 EA
$36,716.00
$36,716.00
6 CIPP LINER IN 18" PIPE
400
LF
$250.00
$100,000.00
7 CIPP LINER IN 36" PIPE
150
LF
$548.00
$82,200.00
8 REMOVE AND REPLACE CATCH BASIN TOP DECK AND LID
1 EA
$16,736.00
$16,736.00
TOTAL
$266,602.00