1 CITY OF GARDEN GROVE
AMENDMENT NO. 1
This Amendment No. 1 is made and entered into this __________________, 2024, by and between the CITY OF GARDEN GROVE, hereinafter referred to as "CITY", and THOMCO CONSTRUCTION, INC. hereinafter referred to as "CONTRACTOR".
WHEREAS, CONTRACTOR and CITY entered into Contract No. P232280, dated April 25, 2023 , to furnish material, equipment, and labor for the Central Cities Navigation Center Project (CCNC), City Project No. CP-1350000-1, as needed (the “Existing Contract”).
WHEREAS, CONTRACTOR and CITY desire to amend the Existing Contract as provided herein.
Now, therefore, it is mutually agreed, by and between the parties as follows:
Section 3.1., COMPENSATION - shall be amended as follows:
Contractor shall be compensated in accordance with scope of work set forth in the Existing Contract. The contract price is hereby increased by Two Hundred Sixty Thousand Dollars and 00/100 ( $260,000.00), for a total not to exceed compensation amount of $4,867,450.00 to cover increased services requested by CITY described in Exhibit A and Attachment 1.
Except as expressly amended hereby, all of the terms and conditions in the Existing Contract remain in full force and effect as originally executed.
[SIGNATURE PAGE FOLLOWS]
2 IN WITNESS WHEREOF, the parties have caused this Amendment No. 1 to the Existing Contract to be executed by their respective officers duly authorized on the date first written above.
Date: _____________ "CITY"
CITY OF GARDEN GROVE
By: ____________________________
City Manager
ATTESTED:
____________________________
City Clerk
Date: _______________________
"CONTRACTOR"
THOMCO CONSTRUCTION, INC.
By: ______________________________
Name: ___________________________
Title: ____________________________
Date: ____________________________
If CONTRACTOR is a corporation, a
Corporate Resolution and/or
Corporate Seal are required. If a
partnership, Statement of
Partnership must be submitted to
CITY.
APPROVED AS TO FORM:
____________________________
Garden Grove City Attorney
________________________
Date
3 Exhibit “A”
COST BREAKDOWN
Tasks Cost
COR – Security Camera $172,724.02
Change Orders $87,275.98
Total $260,000.00