item 10 Award of Contract to National Pools Inc., for the Eastgate Park Swimming Pool Improvement Project (Cost: $200,975.00)(Action Item)

Garden Grove City Council
May 14, 2024

Document
item 10 Award of Contract to National Pools Inc., for the Eastgate Park Swimming Pool Improvement Project (Cost: $200,975.00)(Action Item)
Meeting
May 14, 2024
Body
Garden Grove City Council
Pages
2
Original file
114 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 212/2024
City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 5/14/2024

Subject: Award a contract to National Pools Inc., for Bid S-1324 Eastgate Park Swimming Pool Improvement Project. (Cost: $200,975) (Action Item)

OBJECTIVE

For the City Council to award National Pools Inc. a contract for the Eastgate Park Swimming Pool Improvement Project, which will replace the existing swimming pool plaster and deck coping that has degraded over the years. The final contract price will include $168,475 for furnishing and installing new pool plaster plus a bid alternate in the amount of $32,500 for furnishing and installing new pool skimmers, for a total contract price of $200,975.

BACKGROUND

The Public Works Parks Maintenance Section is responsible for maintaining three municipal pools in the City. These swimming pools are used throughout the year and are visited by many residents for swimming instruction classes and recreational swimming. The Gary Hall swimming pool at Eastgate Park is a heavily-used swimming pool during the summer months (May-September), and it is staffed by a certified pool maintenance operator to maintain pool chemistry and infrastructure.

DISCUSSION

It is paramount to remove and replace the existing plaster, as it has been in place for over fifteen years. Additionally, the recommended life span of swimming pool plaster is anywhere from ten to fifteen years per industry standards. Currently, the swimming pool plaster is pitted, and it is in need of prompt repairs.

The City requested bids for subject project (Bid S-1324), and the following are the results:

Company Name Bid Amount Alternate TOTAL BID
1 National Pools, Inc. $168,475.00 $32,500.00 $200,975.00 2 Ultimate Pool Remodeling,
Inc.
$225,910.00 $27,500.00 $253,410.00
3 California Waters
Development Inc.
$251,566.00 $31,128.00 $282,694.00

Item 212/2024

Page 2 of 2 ends

The project will remove and replace the pool plaster, furnish and install new concrete pool coping, and furnish and install pool skimmers. The Project is expected to be completed before the start of the summer season.

FINANCIAL IMPACT

There is no impact to the General Fund. The Community Services Department has allocated project funding in the Fiscal Year 2023-24 budget (GL 2143101280 – JL CP1181000).

RECOMMENDATION

It is recommended that the City Council:
• Award a contract for Bid S-1324 to National Pools Inc., for the Eastgate Park Swimming Pool Improvement Project to replace the swimming pool plaster and deck coping for the Gary Hall pool at Eastgate Park, in the not -to-exceed amount of $200,975. This total amount includes the bid alternate pricing for furnishing and installing pool skimmers; and
• Authorize the City Manager to sign the contract on behalf of the City, and make minor modifications as appropriate thereto.

ATTACHMENTS:

1. S-1324 Bid Results

2. National Pools Inc - Contractor Proposal

3. Contract